CITY OF KELLER FIVE-YEAR CAPITAL IMPROVEMENTS PROGRAM (CIP) SUMMARY



                                                           FISCAL YEARS
                                                                                                          TOTAL ALL
             PROJECT     PRIOR YEARS  FY 2020-21  FY 2021-22  FY 2022-23  FY 2023-24  FY 2024-25  FY 2025-26
                                                                                                           YEARS

                                                     STREET SYSTEM



                                                       Pavement Seepage
          Street Maintenance                150,000                                                      $           150,000
               Fund
          TOTAL PROJECT   $          150,000   $                     -   $                      -   $                    -   $                    -   $                     -   $                     -   $           150,000
           IMPACT ON O&M  The project is mitigating groundwater seepage on an existing roadway and minimal operating impact is anticipated.



                                                   UPRR Pedestrian Crossing
            General Fund               150,000                                                           $           150,000
          TOTAL PROJECT   $          150,000   $                     -   $                      -   $                    -   $                    -   $                     -   $                     -   $           150,000
           IMPACT ON O&M  The project adds new sidewalks at various railroad crossings and related operational costs can be absorbed in the current budget.


                                                      Vine Street Drainage

            General Fund                 25,000                                                          $             25,000
          TOTAL PROJECT   $            25,000   $                     -   $                      -   $                    -   $                    -   $                     -   $                     -   $             25,000
           IMPACT ON O&M  The project improves existing drainage and minimal operating impact is anticipated.


                                                    Pavement Condition Study
          Street Maintenance                125,000                                                      $           125,000
               Fund
          TOTAL PROJECT   $          125,000   $                     -   $                      -   $                    -   $                    -   $                     -   $                     -   $           125,000
                         The project studies pavement conditions to help prioritize future streets and sidewalks improvements. No direct operational costs are
           IMPACT ON O&M
                         anticipated.

                                                     Shady Grove (KS to S)
            General Fund                       1,000,000             2,000,000          2,000,000        $        5,000,000
          TOTAL PROJECT   $                      -   $       1,000,000   $        2,000,000   $     2,000,000   $                    -   $                     -   $                     -   $        5,000,000

           IMPACT ON O&M  The project is reconstruction of an existing road and minimal operating impact is anticipated.


                                                     Bar Ditch Maintenance
            General Fund                          830,000                                                $           830,000
          TOTAL PROJECT   $                      -   $          830,000   $                      -   $                    -   $                    -   $                     -   $                     -   $           830,000
           IMPACT ON O&M  The project provides capital maintenance of existing bar ditches and minimal operating impact is anticipated.



                                               Bear Creek Bridge Erosion Protection
            General Fund                                      400,000             400,000                $           800,000
          TOTAL PROJECT   $                      -   $                     -   $           400,000   $        400,000   $                    -   $                     -   $                     -   $           800,000
           IMPACT ON O&M  The project provides capital maintenance of an existing bridge and minimal operating impact is anticipated.