CITY OF KELLER FIVE-YEAR CAPITAL IMPROVEMENTS PROGRAM (CIP) SUMMARY



                                                           FISCAL YEARS
                                                                                                          TOTAL ALL
             PROJECT     PRIOR YEARS  FY 2020-21  FY 2021-22  FY 2022-23  FY 2023-24  FY 2024-25  FY 2025-26
                                                                                                           YEARS

                                                     STREET SYSTEM


                                                     2020 Utility Relocations
          Water-Wastewater                150,000                                                        $           150,000
               Fund
          TOTAL PROJECT   $          150,000   $                     -   $                      -   $                    -   $                    -   $                     -   $                     -   $           150,000
           IMPACT ON O&M  The project funds utility relocations for street projects and minimal operating impact is anticipated.


                                                     2021 Utility Relocations
          Water-Wastewater
               Fund                               165,000                                                $           165,000
          TOTAL PROJECT   $                      -   $          165,000   $                      -   $                    -   $                    -   $                     -   $                     -   $           165,000
           IMPACT ON O&M  The project funds utility relocations for street projects and minimal operating impact is anticipated.


                                                        N/S Portal Signs
            General Fund                 50,000                                                          $             50,000
          TOTAL PROJECT   $            50,000   $                     -   $                      -   $                    -   $                    -   $                     -   $                     -   $             50,000

           IMPACT ON O&M  The project funds design and engineering of portal signs on the north and south border.  Minimal operating impact is anticipated.


                                                   Old Town Keller RR Tunnel
            General Fund            3,385,270                                                            $        3,385,270
          TOTAL PROJECT   $       3,385,270   $                     -   $                      -   $                    -   $                    -   $                     -   $                     -   $        3,385,270

           IMPACT ON O&M  The scope of the project has yet to be determined, therefore, operating impacts are unknown.


                                                   Old Town Keller E. /Bates St.
            General Fund               614,730                                                           $           614,730
            Debt Issuance                                           5,000,000         10,000,000         $      15,000,000
             KDC Fund                                         685,000                                    $           685,000
          TOTAL PROJECT   $          614,730   $                     -   $           685,000   $     5,000,000   $    10,000,000   $                     -   $                     -   $      16,299,730
                         The project improves street and related infrastructure on the east side of Old Town Keller and Elm Street. The project includes a pedestrian
                         crossing on 377 and a park on Bates street. The operating impact is related to the estimated annual debt payment.
           IMPACT ON O&M
                                                                                   $      1,302,376   $      1,302,376


                                     FM 1709 and Keller Smithfield Road Intersection Improvements
            General Fund               250,000                                                           $           250,000
          TOTAL PROJECT   $          250,000   $                     -   $                      -   $                    -   $                    -   $                     -   $                     -   $           250,000

           IMPACT ON O&M  The project improves an existing intersection and is partially maintained by TxDOT. Minimal operating impact is anticipated.