CIP AND CAPITAL PROJECTS FUNDS



                   Justification: The existing asphalt pavement in Meadowlark Lane east is failing and
                   the sanitary sewer line is in the front yards of people’s houses.  The project will relocate
                   that sanitary sewer line to the street.


                   Operating Impact:  This street improvement will have little or no impact on operations.
                   It will be funded through the 2017 Certificate of Obligation proceeds.

               ™ Description:  Summertime Lane –
                   Summertime Lane will be reconstructed from
                   Rufe Snow Drive to Carousel Drive. The
                   project includes a complete reconstruction of
                   the street, storm water drainage system,
                   water main improvements, and sanitary
                   sewer improvements. The new street section
                   shall be concrete paving with 4’ wide
                   sidewalks running along both sides of the
                   roadway.

                   Justification: The existing asphalt pavement in Summertime Lane is failing and the
                   water and wastewater lines need to be replaced.

                   Operating Impact:  This street improvement will have little or no impact on operations.
                   It will be funded through the 2017 Certificate of Obligation proceeds.

                                         FY2020-2021 SIDEWALK PROGRAM


               ™ Description:  Approximately 5,000 square feet of sidewalks will be maintained this
                   fiscal year.  The City identifies various sidewalks annually for replacement.

                   Justification:  Safe, pedestrian-friendly neighborhoods are a priority of our community.
                   An important component of this is the City’s Sidewalk Program which is developed to
                   provide for the maintenance of sidewalks within the City of Watauga.


                   Operating Impact: The Sidewalk program this year is funded by a transfer from the
                   General Fund to the General Capital Projects Fund.

                                 FY2020-2021 STORM DRAIN PROJECTS DISCUSSION


               ™ Description:  The Whitley Road Phases I-IV projects will make major storm drain
                   improvements along Whitley Road. Currently, there are ditches along Whitley Road that
                   carry the storm water. This storm water will be put under Whitley Road and carried by
                   pipes.

                   Justification:  When we widen Whitley Road, there won’t be room within the right of
                   way for the ditches to carry the storm water. Adding curbs and curb inlets allow us to
                   carry the storm water underground.