Page 291 - N. Richland Hills Capital Budget
P. 291

Schedule 11
                                                    2019-20 Budget Revisions
                                                       Budget Summary



                                                                       Adopted        Budget         2019-20
                  Project                   Project                    Through        Revision       Revised
                  Number                     Name                      2019-20        2019-20        Budget
             STREET & SIDEWALK CAPITAL PROJECTS
                  CDBG19    Schiller Drive Reconstruction                  $35,000        ($6,000)       $29,000
                  ST2003    Northeast Parkway / Davis Blvd. Traffic Signal  380,000       (25,000)       355,000
                  ST2005    Northeast Parkway Extension                    790,000         25,000        815,000
                  ST1304    Smithfield Road (Davis/Mid-Cities)            3,343,640       (68,170)      3,275,470
                  ST1701    Vance and Glenview Signal Upgrades             241,692         74,170        315,862
                            Sub-Total                                    $4,790,332          $0        $4,790,332
             DRAINAGE CAPITAL PROJECTS
                  DR1902    Street Drainage Improvements Project (2019)   $100,000         ($102)        $99,898
                  DR1801    Snow Heights Drainage Improvements Project     320,000         (4,567)       315,433
                            Sub-Total                                     $420,000        ($4,669)      $415,331
             PARKS & RECREATION CAPITAL PROJECTS
                  PK1802    Hometown Lakes Pedestrian Bridge Trail Connections  $80,000   ($2,811)       $77,189
                  PK1606    Park System Signange                           479,486         (5,000)       474,486
                  PK1806    Trail and On-Road Safety Projects              730,543          5,000        735,543
                  PK1901    Annual Tree Planting 2019                       45,000         (8,840)        36,160
                  PK1603    Northfield Park Redevelopment                 6,125,312        (5,133)      6,120,179
                  PK2005    Richland Tennis Center Infrastructure Improvements (2020)  100,000  0        100,000
                  PK1902    Linda Spurlock Park Renovation                1,000,000        35,000       1,035,000
                  PK1904    Park Infrastructure Maintenance 2019           285,907         (9,954)       275,953
                  PK2004    Park Infrastructure Maintenance 2020           190,000        (25,046)       164,954
                            Sub-Total                                    $9,036,248       ($16,784)    $9,019,464
             UTILITY CAPITAL PROJECTS
                  UT2009    Water Impact Fee Project                          $0          $21,000        $21,000
                  UT2010    Sewer Impact Fee Project                           0           21,000         21,000
                  UT1905    Small Water Main Replacements (2019)           440,000         (4,989)       435,011
                  UT1903    Miscellaneous Water/Sewer Main Replacement (2019)  445,000      4,989        449,989
                            Sub-Total                                     $885,000        $42,000       $927,000
             MAJOR CAPITAL EQUIPMENT
                  FS2004    Fuel System Enhancements                      $163,000       ($128,000)      $35,000
                  IT1401    Cell Phone Signal Boosters in NRH Centre        98,000        (98,000)           0
                  FS1910    Utility Tractor Replacement                     34,500         20,500         55,000
                  FS1902    Distributor Truck Replacement (Unit 681)       200,000          (211)        199,789
                  FS1904    Pothole Patcher                                202,588          (652)        201,936
                  FS1909    Utility Tractor Replacement                     55,000        (23,763)        31,237
                  FS1911    Vac-Con Truck                                  402,000            (5)        401,995
                  FS2002    Backhoe Replacement                            140,000        (36,000)       104,000
                  FS2003    Backhoe Replacement                            140,000        (38,600)       101,400
                  FS2006    Utility Tractor Replacement                     65,000        (33,078)        31,922
                  FS2008    Wheel Loader                                   220,000        (56,000)       164,000
                  FS1901    Crack Sealing Machine                           95,000        (26,592)        68,408
                  FS2007    Wheel Loader Replacement (Unit 685)            220,000         (5,000)       215,000
                  FS2005    Roller Replacement (Unit 6620)                  65,000          5,000         70,000
                  FS2007    Wheel Loader Replacement (Unit 685)            215,000        (72,000)       143,000
                  FS1903    Dump Truck Replacement                         120,412            0          120,412
                  IS1502    Replacement of CAD/RMS Public Safety Software Platform  3,020,000  (81,000)  2,939,000
                            Sub-Total                                    $5,455,500      ($573,401)    $4,882,099
             AQUATIC CAPITAL PROJECTS
                  WP1901    General Facility Improvements 2019            $100,000        ($11,279)      $88,721
                            Sub-Total                                     $100,000        ($11,279)      $88,721
             FACILITY CAPITAL PROJECTS
                  FC1701    Overhead Door Replacement                      $52,000        ($1,000)       $51,000
                  FC1702    Overhead Door Safety Edges & Remote Control Assemblies  68,800  (900)         67,900
                  FC1902    Permanent Records Roof Replacement $ Building Envelope Seal  78,000  (6,500)  71,500
                  FC1903    Replacement of HVAC Systems at Fire Stations #1 and #4  59,000  (141)         58,859
                  FC1904    Upgrade/Remodel of Public Works Restroom        75,000          6,500         81,500
                            Sub-Total                                     $332,800        ($2,041)      $330,759
             ECONOMIC DEVELOPMENT PROJECTS
                  ED0601    TIF 1 Expansion - Intersection Improvements/Utility Buria  $3,000,000  ($432,715)  $2,567,285
                  ED1002    Loop 820 Redevelopment 2010                   1,595,572        45,724       1,641,296
                  ED1503    TOD Land Management                           1,200,000        89,033       1,289,033
                            Sub-Total                                    $5,795,572      ($297,958)    $5,497,614