STREET BOND FUND
FUNDED PROJECTS
Operating Impact
Project Description Project Justification Status 09/30/20
9/30/20
The proposed project will be determined by Hurst will receive approximately $165,000 in CDBG Project is in the planning O&M impact due to
staff and council prior to submittal to Tarrant funds and will be required to provide matching funds phase of the project and reduced maintenance
County in 2020. Instead of giving each City for the project. This grant has been a steady source is scheduled to be costs with construction of
participating in the CDBG county-wide of alternate funding for improving the City's complete sometime in new street.
program a smaller amount each year, they infrastructure in its oldest areas. fiscal year 2020-2021.
are offering twice as much but only every
other year.
This project will widen Pipeline Road from This project is necessary to improve traffic flow This project is currently O&M impact due to
Lorean Branch Bridge to Harrison Lane. along Pipeline Road and is a segment of an overall in planning and ROW reduced maintenance
project to reconstruct and widen Pipeline Road from acquisitions. costs with construction of
Billie Ruth Drive East to Brown Trail. Tarrant County new street.
has pledged to participate in 50% of the construction
cost.
This project consists of the reconstruction of This project is necessary to maintain a roadway Debt was issued in the O&M impact TBD as
city streets to be determined by the City system that meets the criteria set by the City of fall of 2018-2019 and will street improvements
Manager. Hurst standards and helps achieve the monetary be assigned as needed determined.
level of commitment recommended in the recent by the City Manager
Pavement Management Analysis report by
Infrastructure Management Services (IMS) dated
December 2017.