FY 2020-21 APPROVED OPERATING BUDGET
                GENERAL FUND - CITY MANAGER
                INFORMATION TECHNOLOGY DIVISION SUMMARY
                100-101-002





                                                             2017-18   2018-19    2019-20   2019-20    2020-21
                EXPENDITURES BY OBJECT                        Actual    Actual    Budget   Estimate   Approved

                Personnel                                      1,132,170        1,169,838        1,302,793        1,161,263        1,355,648
                Supplies                                            65,841             48,488             42,650             30,214             37,100
                Maintenance                                         93,122             77,407           365,627           167,776           394,127
                Services                                          550,406           657,034           687,209           633,642           651,980
                Capital Outlay                                            -             44,149                   -             97,555                   -


                Total                                          1,841,539        1,996,916        2,398,279        2,090,450        2,438,855



                OBJECTIVES


                - Provide excellent customer service and communication to City Departments.
                - Provide technically competent project assistance to City Departments to ensure successful delivery of their projects.
                - Provide a secure voice and data network with minimal downtime and quick response times.
                - Keep network equipment replaced on a consistent schedule.
                - Keep infrastructure capacity ahead of increasing demands.




                                                             2017-18   2018-19    2019-20   2019-20    2020-21
                PERFORMANCE INDICATORS                        Actual    Actual    Budget   Estimate   Approved

                Number of work orders completed                       5,433               4,653               3,600               3,600               3,600
                Number of hours spent working on GTG projects and              10,000               1,694               1,200               1,700               1,850
                internal PMO projects
                Number of computers receiving a software patch or service                1,500               2,292               2,300               2,500               2,500
                pack
                Number of GIS map requests completed                     529                  371                  200                  250                  300
                Number of desktop computers replaced or upgraded                  200                    20                    50                    50                  100
                Number of server operating system upgrades, physical                   375                    50                  100                    50                    50
                units replaced, physical units added, and logical servers
                 dd d
                Number of LAN and Wireless units added,  replaced, and                     35                    25                    20                    20                    20
                number of new locations designed and implemented
                Number of projects completed                               35   10    10         6         10












                                                             67