Page 477 - FY 2009 Proposed Budget
P. 477
Public Safety
Goal 2: Mitigate Flood Risks and Protect Stormwater Infrastructure
Objective 1: Plan and Implement Stormwater Projects
Project Performance Measure(s) City Service Team (Department)
Core Stormwater Projects Implement projects that mitigate flooding Economic Development and
PS concerns Capital Investment (PWT)
2.1.1
Summary:
Stormwater Projects are funded through the Stormwater
Utility Fee and are included in the annual capital budget. The
projects listed below are expected to begin or complete
construction during FY 2020. Project milestones listed in the
table will be updated as they occur during the year.
Update:
The Matthews Court Drainage Improvements Phase 1 and 2
construction, which began in June of 2020, is proceeding on
schedule. The improvements in Randol Mill Park and along
Randol Mill Road are scheduled to be completed December of
2020.
Kee Branch Trib 4 is being constructed in two phases.
Construction of the segment in Deaver Park (Phase 1) will
begin in November of 2020 while easements are acquired in
the segment between Bradley Lane and Andalusia Trail (Phase
2).
The Harvest Hills project is split into a channel project (Phase
1) and a neighborhood improvements project (Phase 2). Phase
1 is in the final design phase and easement acquisitions will
begin in FY 2021. Phase 2 design will also begin in FY 2021.
The Country Club Channel and Drainage Improvements
The 2019 Ditches project design phase is nearing completion. Project, featured in the above picture, as well as bridge
A contract modification was completed to locate underground and pavement maintenance on Park Row were
utilities that may conflict with the final design. The project completed in September 2020.
will be bid in early 2021.
Stormwater Capital Improvement Project Estimated Actual Bid Estimate Actual
Bid Dates Dates Completion Completion
Sublett Creek Neighborhood Drainage Improvements Apr. 2018 Nov. 2018 Nov. 2019 Dec. 2019
Washington Drive Erosion Project Sept. 2018 Nov. 2019 Mar. 2021
Country Club Channel and Drainage Improvements Sept. 2018 June 2019 Apr. 2020 Sept. 2020
Matthews Court Drainage Improvements Phase 1 Dec. 2018 Dec. 2019 Dec. 2021
Matthews Court Drainage Improvements Phase 2 June 2019 Dec. 2019 Dec. 2021
Kee Branch Trib 4 Erosion Phase 1 June 2019 Aug. 2020 Apr. 2021
Kee Branch Trib 4 Erosion Phase 2 Feb. 2021
Kee Branch Trib 1 Erosion Aug. 2019
Harvest Hills Drainage Improvements Phase 1 Aug. 2019
Lower Johnson Creek Dredging Dec. 2019 Dec. 2019 Oct. 2020
2019 Ditches Project June 2020
126