      WATER IMPACT FEE FUnD


                                City of Southlake FY 2020 CIP Project Status Form

                                Upsize water lines along West Park Circle off of T.W. King

           DEPARTMENT: Public Works
           PROJECT
           LOCATION:   West Park Circle

           PROJECT TIMELINE: Oct 2019  to  Sept 2020
           DESCRIPTION:
           Funding is requested for the engineering design and construction of 8-inch water lines
           along W. Park Circle, off T.W. King Road, to replace existing, substandard 2-inch water
           lines. Replacement of the existing lines will include the addition of fire hydrants for
           added protection of existing and future homes.







                                                                    New Request     Continuation Project  Joint Use
           JUSTIFICATION:                                           Mandated /    Replacement / Major   Community
                                                                                  Rehab or Protection
                                                                    Public Health /
           Project will upgrade water service ability and add fire hydrants to the location,     Safety     of Capital Stock     Need / Service
                                                                                                   Enhancement
           increasing level of service and public safety.
                                                                     Compliant with 2030/2035 Comprehensive Plan Element?
                                                                    List (incl ref #):
           ALTERNATIVES / IMPACTS IF PROJECT IS NOT FUNDED:         COMPANION PROJECT? If yes, please explain:
           Service will continue to be provided via substandard, 2-inch water lines and without fire  N/A
           hydrants within the subdivision for protection of existing and future homes.
                                                                    REVENUE GENERATING? If yes, please explain:
           STRATEGIC FOCUS AREA: Safety & Security, Infrastructure
                                                                    N/A
           FUND:  Water Impact Fee
                                                     EXPENDITURE SCHEDULE
               PROJECT ELEMENT  TOTAL PRIOR  2020     2021     2022     2023     2024     UNFUNDED    TOTAL
            PLANNING / FEASIBILITY STUDY                                                               0
                ENGINEERING & DESIGN  50                                                               50
                            LAND                                                                       0
                          TESTING                                                                      0
                     CONSTRUCTION           300                                                        300
                           OTHER                                                                       0
                           TOTAL   50       300       0         0        0        0         0          350
                                                     OPERATIONAL IMPACT
               PROJECT ELEMENT  TOTAL PRIOR  2020     2021     2022     2023     2024    UNFUNDED     TOTAL
                  MAINTENANCE COSTS          5        5         5        5        5         5          30
                   PERSONNEL COSTS  5                                                                  5
                           TOTAL    5        5        5         5        5        5         5          35
                                                      FUNDING SCHEDULE
                FUNDING SOURCE  TOTAL PRIOR  2020     2021     2022     2023     2024     UNFUNDED    TOTAL
                     GENERAL FUND                                                                      0
                           CCPD                                                                        0
                           CEDC                                                                        0
             HOTEL OCCUPANCY TAX FUND                                                                  0
              PARK DEDICATION FEE FUND                                                                 0
                    PUBLIC ART FUND                                                                    0
             ROADWAY IMPACT FEE FUND                                                                   0
             SANITARY SEWER IMPACT FEE                                                                 0
                           SPDC                                                                        0
                           SWUS                                                                        0
                       UTILITY FUND                                                                    0
               WATER IMPACT FEE FUND  50    300                                                        350
                           TOTAL   50       300       0         0        0        0         0          350
           CCPD: CRIME CONTROL & PREVENTION DISTRICT                            SPDC: SOUTHLAKE PARKS DEVELOPMENT CORPORATION
           CEDC: COMMUNITY ENHANCEMENT & DEVELOPMENT CORPORATION                      SWUS: STORMWATER UTILITY SYSTEM FUND
                                    Funding is represented in thousands of dollars (000s).  Example:  3,776 = $3,776,000