                                   City of Southlake FY 2020 CIP Project Status Form
                              City Roadway Intersection Capacity Improvements (GF6 Companion)

               DEPARTMENT: Public Works
               PROJECT
               LOCATION:  FM 1938 at W. Continental Boulevard
               PROJECT TIMELINE: Oct 2019  to  Sept 2020
               DESCRIPTION:
               Funding is requested for right of way, new traffic signal, right turn lane and other paving
               improvements to improve alignment of this intersection based on recommendations of
               preliminary engineering study of this intersection.








                                                                        New Request     Continuation Project  Joint Use
               JUSTIFICATION:                                           Mandated /    Replacement / Major   Community
                                                                        Public Health /   Rehab or Protection      Need / Service
               These improvements will also help alleviate current traffic backups during peak hours  Safety  of Capital Stock  Enhancement
               on west bound Continental Boulevard at FM 1938.
                                                                        Compliant with 2030/2035 Comprehensive Plan Element?

                                                                        List (incl ref #):
               ALTERNATIVES / IMPACTS IF PROJECT IS NOT FUNDED:          COMPANION PROJECT? If yes, please explain:
               Roadway will remain at current capacity, resulting in the continual increase in traffic  General Fund GF6
               congestion during peak hours.
                                                                        REVENUE GENERATING? If yes, please explain:
               STRATEGIC FOCUS AREA: Mobility, Infrastructure
                                                                        N/A
               FUND:  Roadway Impact Fee, General
                                                        EXPENDITURE SCHEDULE
                   PROJECT ELEMENT  TOTAL PRIOR  2020    2021      2022     2023     2024    UNFUNDED     TOTAL
                PLANNING / FEASIBILITY STUDY                                                               0
                    ENGINEERING & DESIGN                                                                   0
                               LAND                                                                        0
                             TESTING                                                                       0
                         CONSTRUCTION  800      300      300                                              1,400
                              OTHER                                                                        0
                              TOTAL   800       300      300       0        0         0         0         1,400
                                                         OPERATIONAL IMPACT
                   PROJECT ELEMENT  TOTAL PRIOR  2020    2021      2022     2023     2024    UNFUNDED     TOTAL
                     MAINTENANCE COSTS                    10       10       10       10         10         50
                       PERSONNEL COSTS                                                                     0
                              TOTAL    0         0        10       10       10       10         10         50
                                                          FUNDING SCHEDULE
                   FUNDING SOURCE   TOTAL PRIOR  2020    2021      2022     2023     2024    UNFUNDED     TOTAL
                         GENERAL FUND           900      1,100                                            2,000
                               CCPD                                                                        0
                               CEDC                                                                        0
                HOTEL OCCUPANCY TAX FUND                                                                   0
                 PARK DEDICATION FEE FUND                                                                  0
                        PUBLIC ART FUND                                                                    0
                 ROADWAY IMPACT FEE FUND  800   300      300       0        0         0         0         1,400
                SANITARY SEWER IMPACT FEE                                                                  0
                               SPDC                                                                        0
                               SWUS                                                                        0
                          UTILITY FUND                                                                     0
                   WATER IMPACT FEE FUND                                                                   0
                              TOTAL   800       1,200    1,400     0        0         0         0         3,400
               CCPD: CRIME CONTROL & PREVENTION DISTRICT                           SPDC: SOUTHLAKE PARKS DEVELOPMENT CORPORATION
               CEDC: COMMUNITY ENHANCEMENT & DEVELOPMENT CORPORATION                      SWUS: STORMWATER UTILITY SYSTEM FUND
                                    Funding is represented in thousands of dollars (000s).  Example:  3,776 = $3,776,000