Utility Fund
                                                                                                                    CIP

                                                                                                           UTILITY FUnD



               SPIN   Neigh-  bor-  hood  1                     1                      5              8

                Comprehen-  sive Plan   Reference  Water   System   Master Plan   #14-WWS10-  Tier 2  Sustainability   Master Plan  Water   System   Master Plan   #18 -WWS9-  Tier 2  Water   System    Master Plan   #21-WWS9   -Tier 2



              Project's   Impact to   Annual   Operating   Budget  $5,000  $5,000      $10,000        $10,000



              Descrip-  tion of   Annual   Impact on   Operating   Budget  Increase in   preven-  tive and   corrective   mainte-  nance.  Increase in   preven-  tive and   corrective   mainte-  nance.  Increase in   preven-  tive and   corrective   mainte-  nance.  Increase in   preven-  tive and   corrective   mainte-  nance.


                FY 2020   Cumula-  tive  $2,150,000             $2,150,000             $2,150,000     $2,150,000




                 Total               $1,600,000                 $1,600,000             $1,250,000     $800,000


                Beyond /   Unfunded  $0                         $0                     $0             $0



                 FY 2024             $0                         $0                     $0             $0


                 FY 2023             $1,350,000                 $1,350,000             $0             $0



                 FY 2022             $200,000                   $200,000               $1,050,000     $700,000



                 FY 2021             $50,000                    $50,000                $200,000       $100,000


                 FY 2020             $0                         $0                     $0             $0



                Total Prior   Funding  $0                       $0                     $0             $0



                          Funding is requested for   right of way, engineering   design and construction   of an 8-inch water line to   and E. Bob Jones Road.   This project will create   a looped water system,   fire protection within this   region. This item was not   Freese and Nichols, Inc.  Funding is requested for   the dead-end water lines   located at Walnut Grove   and the Bob Jones Dog   a looped water system,   fire protection within this   region. This item was not   Free
                 Description    connect the dead-end water  lines located at Brooks Court   improving water quality and   part of Southlake 2030 but  later identified in the Water  Quality Study produced by   right of way, engineering de- sign and construction of an  8-inch water line to connect   Park. This project will create   improving water quality and   part of Southlake 2030 but  later identified in the Water  Quality Study produced by   design and construction of   Shady Oaks





                 Project Name     8-inch Water   line along   Bob Jones   Road to Wal-  nut Brooks  8-inch Water   line from   Walnut Grove   terminus to   E. Bob Jones   Dog Park  12-inch   Water line   along Shady   Oaks Drive   from Fox   Glen to West   Dove Road   (Phase II)  12-inch   Water line   along East   Continental   Boulevard to   Breeze Way




                 Fund               Utility   Fund             Utility   Fund         Utility   Fund  Utility   Fund


                 Project #           UF10                       UF11                   UF12           UF13