Street & Sidewalk Capital Projects
                                            Vance and Glenview Signal Upgrade
                                                           ST1701




            This project consists of replacing the existing span wire signal at the intersection of Vance Road and Glenview Drive with pole
            mounted signals. This project also includes the installation of pedestrian signal heads and striping at the intersection. This
            project has been approved for funding through the HSIP (Highway Safety Improvement Program) grant which is 90% federal
            funding and 10% local funding. The 90% coverage of federal funds is only for construction costs. This project will be let through
            TxDOT as the grant is disseminated through TxDOT.

            As part of the City's submission for the HSIP grant, the City discovered from 2012-2014, there was one accident near this
            intersection with one fatality, one incapacitating injury and two non-incapacitating injuries.

            Note: Funding source is Grant from TxDOT (COG is fiduciary agent for this grant) and Reserves from project savings.





           Professional Services
           Engineering                            10/2016                                 04/2018      04/2019
           Land/ROW Acquisition
           Construction                           10/2016                                 12/2018      12/2019
           Other



            Additional funding for this project is needed for unplanned environmental consulting services. Funds are available from project
            savings in ST0102.









            Federal/State Grants                    $180,000                   $180,000                  $180,000
            Reserves                                  50,000        7,303        57,303                   $57,303
                                                                                     0                         $0
                                                                                     0                         $0
                                                                                     0                         $0
                                                    $230,000       $7,303      $237,303          $0      $237,303

                                                                                    $0                         $0
             Professional Services
             Engineering/Design                       30,000        7,303        37,303                   $37,303
             Land/ROW Acquistion                                                     0                         $0
             Construction                            200,000                    200,000                  $200,000
             Other                                                                   0                         $0
                                                    $230,000       $7,303      $237,303          $0      $237,303



            No operating impact is expected.