Page 283 - NRH FY20 Approved Capital Budget
P. 283

Schedule 11
                                                    2018-19 Budget Revisions
                                                       Budget Summary



                                                                       Adopted        Budget         2018-19
                  Project                   Project                    Through        Revision       Revised
                  Number                     Name                      2018-19        2018-19        Budget
             STREET & SIDEWALK CAPITAL PROJECTS
                  ST0102    Rufe Snow Improvements (Karen to 820)        $1,475,950       ($7,303)      $1,468,647
                  ST0401    Davis Blvd/Mid-Cities Blvd Intersection      $7,359,231      $330,769       7,690,000
                  ST1701    Vance and Glenview Signal Upgrade              230,000          7,303        237,303
                  ST1201    Rufe Snow Drive & Glenview Drive Intersection Improvements  1,685,000  (4,389)  1,680,611
                  ST1701    Vance and Glenview Signal Upgrade              237,303          4,389        241,692
                            Sub-Total                                    $10,987,484     $330,769      $11,318,253
             DRAINAGE CAPITAL PROJECTS
                  DR1701    Walker Branch Channel Repair                  $627,850       ($320,000)      $307,850
                  DR1503    Calloway Branch Channel Repair Project        1,126,258       320,000       1,446,258
                            Sub-Total                                    $1,754,108          $0         $1,754,108
             PARKS & RECREATION CAPITAL PROJECTS
                  PK1603    Northfield Park Renovation                   $6,116,659        $8,653       $6,125,312
                  PK1504    Northfield Park Security Lights/Electrical System  $35,000    ($8,653)        26,347
                  PK1201    Adventure World Playground Renovation         $653,239          ($667)       652,572
                  PK1401    Barfield/Cotton Belt Trail Connector           $65,000          ($932)        64,068
                  PK1805    Iron Horse Pump House A                       $100,000        ($2,116)        97,884
                  PK1703    Park Infrastructure Maintenance 2017          $257,000          ($308)       256,692
                  PK1904    Park Infrastructure Maintenance 2019           284,000          1,907        285,907
                  PK1701    Barfield Family Foundation Grant Program        50,000        (30,717)        19,283
                  PK1801    Green Valley Raceway Historical Area            30,000         30,717         60,717
                            Sub-Total                                    $7,590,898       ($2,116)      $7,588,782
             UTILITY CAPITAL PROJECTS
                  CDBG18    Meadow Court Road Reconstruction (CDBG)       $308,456        ($10,878)      $297,578
                  UT1804    Telemetric Water Meter Annual Maintenance (2018)  400,000        (64)        399,936
                  UT0201    Big Fossil Creek Wastewater Outfall           1,200,000        31,604       1,231,604
                  UT1704    Sanitary Sewer System Trunk Line Rehabilitation  125,000      (31,604)        93,396
                  UT1802    Miscellaneous Water/Sewer Main Replacements (2018)  420,000    50,886        470,886
                  UT1803    Small Water Main Replacements (2018)           420,000        (50,886)       369,114
                  UT1702    Small Water Main Replacements (2017)           420,000        (29,483)       390,517
                  UT1803    Small Water Main Replacements (2018)           369,114         27,049        396,163
                  UT1704    Sanitary Sewer System Trunk Line Rehabilitation  93,396         4,724         98,120
                  UT1604    Sanitary Sewer Line Replacements (Crabtree & Onyx N.)  125,000  (4,724)      120,276
                            Sub-Total                                    $3,880,966       ($13,376)     $3,867,590
             MAJOR CAPITAL EQUIPMENT
                  FS1802    Backhoe Replacement (Unit #479)               $125,000        ($34,655)      $90,345
                  FS1903    Dump  Truck Replacement (Unit 6617)           $120,000          $412         120,412
                  FS1904    Pothole Patcher Replacement (Unit 6609)       $210,000          ($412)       209,588
                  FS1803    Bucket Truck Replacement Unit 602             $220,000        ($85,243)      134,757
                  FS1801    Ambulance Replacement Unit 973                $362,232        ($2,681)       359,551
                  FS1907    Skid Steer Loader Replacement Unit  6630       $90,000        ($10,550)       79,450
                  FS1908    Street Sweeper Replacement Unit 6613           $70,000        ($18,000)       52,000
                  FS1905    NRH/Senior Centre Accessible Van               $62,000        ($1,021)        60,979
                  FS1906    NRH/Senior Centre Accessible Van               $62,000        ($1,021)        60,979
                  FS1904    Pothole Patcher Replacement (Unit 6609)       $209,588        ($7,000)       202,588
                  FS1911    Vac-con Replacement (Unit 5522)               $395,000         $7,000        402,000
                  IS1402    Replacement of Fuel Management Software System  $135,025      ($4,289)       130,736
                  IT1701    Enterprise Computer System Replacement       $3,000,000      $173,980       3,173,980
                            Sub-Total                                    $5,060,845       $16,520       $5,077,365
             AQUATIC CAPITAL PROJECTS
                  WP1801    General Facility Improvements (2018)          $100,000        ($2,661)       $97,339
                  WP1802    Main Filtration Replacement                    600,000         (8,513)       591,487
                            Sub-Total                                     $700,000        ($11,174)      $688,826
             FACILITY CAPITAL PROJECTS
                  FC1803    Fire Maintenance Awning                        $60,000          ($250)       $59,750
                            Sub-Total                                      $60,000          ($250)       $59,750
             ECONOMIC DEVELOPMENT PROJECTS
                  ED1901    Davis Boulevard Development 2019                  $0         $450,000        $450,000
                            Sub-Total                                         $0         $450,000        $450,000






                                                             263