Page 240 - NRH FY20 Approved Capital Budget
P. 240

Major Capital Equipment Capital Projects
        Department                                             Project Title                         Project Number
        Fleet Services                              Dump Truck Replacement (Unit 6617)                    FS1903
        Project Description
        This is for the replacement of a 2004 Chevrolet Kodiak tandem dump truck Unit 6617 assigned to the Public Works Street Division.










        Project Justification
        All equipment is evaluated for replacement based on frequency of use, the number of like equipment in the fleet, equipment
        condition, and the availability of parts and service. The dump truck will be 15 years old when replaced with an estimated 100,000
        miles.  The replacement dump truck would be equipped with an energy-efficient clean-burning diesel engine which meets the
        replacement guidelines of the Clean Fleet Vehicle Program.

        Funding source is Equipment Service Fund Reserves (510).












        Project Schedule        Beginning Date  Ending Date  History       Fiscal Year   Amount
        Professional Services                             Adopted Budget    2018-19       $120,000
        Engineering/Design         10/2018      11/2018   Revision          2018-19          $412
        Land/ROW Acquisition                              Total                           $120,412
        Construction               12/2018      05/2019
        Other
        Total Schedule             10/2018      05/2019
        Sources of Funds          To Date    2019-20 Budget 2020-21 Estimate  2021-Completion  Total Funding
        General Obligation Bonds
        Certificates of Obligation
        Federal/State Grants
        Reserves                      120,412           0             0             0      $120,412
        Sales Tax
        Other
        Total Funding                $120,412          $0            $0            $0      $120,412
        Project Costs             To Date    2019-20 Budget 2020-21 Estimate  2021-Completion  Total Cost
        Professional Services
        Engineering/Design
        Land/ROW Acquisition
        Construction                  120,412           0             0             0      $120,412
        Other
        Total Costs                  $120,412          $0            $0            $0      $120,412
        Operating Impact
        None


        Fiscal Year                2019-20       2020-21      2021-22       2022-23       2023-24     Total Impact
        Amount                            $0           $0            $0            $0            $0            $0
        Total Operating Impact            $0           $0            $0            $0            $0            $0




                                                             220