Page 237 - NRH FY20 Approved Capital Budget
P. 237

Major Capital Equipment Capital Projects
        Department                                             Project Title                         Project Number
        Information Services                      Cell Phone Signal Boosters in NRH Centre                IS1401
        Project Description
        This project will provide signal boosters for cellular phones in NRH Centre by installing a DAS (Distribution Antennae System)
        Network.









        Project Justification
        NRH Centre patrons and members experience either a weak or non-existent cell phone signal throughout the facility.  It is theorized
        the building materials used to construct the facility interfere and block cell phone signals.  NRHC staff receive complaints, on a daily
        basis, of the problems patrons are experiencing.  The DAS network will provide the equipment for a continuous signal.  This signal
        will be provided for the three major cell phone carriers-AT&T, Sprint & Verizon.

        Project funding sources are $31,000 from project savings ($14,000 from unspecified Park Project Savings and $17,000 from
        unspecified Information Services), and $67,000 from Information Services reserves.











        Project Schedule        Beginning Date  Ending Date  History       Fiscal Year   Amount
        Professional Services                             Adopted Budget    2013-14        $98,000
        Engineering/Design                                Total                            $98,000
        Land/ROW Acquisition
        Construction
        Other                      10/2013      12/2018
        Total Schedule             10/2013      12/2018
        Sources of Funds          To Date    2019-20 Budget 2020-21 Estimate  2021-Completion  Total Funding
        General Obligation Bonds
        Certificates of Obligation
        Federal/State Grants
        R  e  s  e  r  v  e  s        9  8  ,  0  0  0  0             0             0       $98,000
        Sales Tax
        Other
        Total Funding                 $98,000          $0            $0            $0       $98,000
        Project Costs             To Date    2019-20 Budget 2020-21 Estimate  2021-Completion  Total Cost
        Professional Services
        Engineering/Design
        Land/ROW Acquisition
        Construction
        Other                         98,000            0             0             0       $98,000
        Total Costs                   $98,000          $0            $0            $0       $98,000
        Operating Impact
        Hardware Maintenance.


        Fiscal Year                2019-20       2020-21      2021-22       2022-23       2023-24     Total Impact
        Amount                            $0           $0            $0            $0            $0            $0
        Total Operating Impact            $0           $0            $0            $0            $0            $0




                                                             217