CITY OF HURST
ENTERPRISE FUND PUBLIC WORKS 0669 WASTEWATER
• Annually sample commercial and industrial sites to manage the surcharge program and
reduce wastewater treatment charges.
0-3 Short Term
Performance Measures: PY Actual CY Estimate Projected
Input:
Total Operating Budget $ 6,596,964 $ 7,245,764 $ 7,274,245
Sewer Treatment Costs to Fort
Worth $2,386,193 $2,693,588 $2,492,979
Workload/Output:
Sewer mains cleaned (%) 24% 30% 40%
Wastewater lines replaced (Feet) 0 3,150 5,000
Manholes inspected annually 2,440 2,500 2,500
Manholes repaired annually 23 25 25
Effectiveness:
Total sanitary sewer complaint calls
reported as sanitary sewer
overflows to the TCEQ 7 15 10
Sanitary sewer main stoppages
annually 29 21 25
Sanitary sewer overflows reported
to TCEQ 7 15 10
Efficiencies:
Average response time to calls
concerning wastewater problems
during working hours (min) <30 <30 <30