Page 115 - Haltom City FY20 Approved Budget
P. 115

City of Haltom City Annual Budget, FY 2020
                                                                               Capital Projects Funds



               Fiscal Year 2020 Capital Plan

               The  total  of  the  capital  projects  planned  in  the  Capital  Projects  Funds  for  FY2020  is
               $19,338,203.   The Budget Summary of the Capital Projects Funds is listed below:



                    Capital Project Fund      Actual 2018   Adopted 2019    Projected 2019   Adopted 2020
                Street Reconstruction                3,975,493             4,478,803           4,727,736                8,515,961
                Capital Improvement                  1,869,167             6,412,000           6,673,732                   910,000
                Capital Replacement                  1,217,281                506,000              524,000                   719,000
                Water & Sewer Utility Projects           7,955,467             1,830,000           1,700,998                7,397,633
                Water & Sewer Impact Fees               291,462                 50,000              266,612                          -
                Drainage Capital Projects               611,559                262,000              276,000                1,795,609
                Total Revenue                         15,920,429            13,538,803          14,169,078                  19,338,203

               A matrix of the FY2020 expenditures is listed below:


                                             Vehicles /                      Water &
                    Capital Projects Funds                Streets    Parks             Drainage      Total
                                             Equipment                        Sewer
                Street Reconstruction                         8,515,961                                  8,515,961
                Capital Improvement                                     910,000                              910,000
                Capital Replacement                      719,000                                             719,000
                Water & Sewer Utility Projects                                 7,397,633                 7,397,633
                Water & Sewer Impact Fees                                                                             ‐
                Drainage Capital Projects                                                   1,795,609        1,795,609
                    Total Expenditures           719000     8515961   910000  7397633      1,795,609      19,338,203

               Capital Expenditures and Impact on Operating Costs

               Most  of  the  capital  improvement  projects  are  recurring  (reconstruction/replacement)
               expenditures since the City is a matured city with aged streets, water and sewer systems.
               The City rarely adds new roads and or new infrastructure for expansion.  Most of the
               reconstruction expenditures on capital project do not have significant impact on operating
               cost.

               For  non-recurring  (expansion)  capital  outlays,  the  impact  upon  operations  of  these
               improvements is reflected in the additional cost of maintaining parks, streets and drainage
               systems.

               Replacement of storm sewers, curb and gutters does not reduce the annual budget for
               maintenance.  It does allow these scarce dollars to be allocated to other projects for up
               to 15 years.  Every mile of road in which the City rebuilds the storm sewers, curb and
               gutter allows the City to shift nearly $40,000 in maintenance materials and labor to other
               needed  projects.    Replacing  worn  and  damaged  water  lines  reduces  lost  water  and
               increases customer billing.  Each 1% of lost water that is captured through capital outlay
               is worth about $90,000 at current commodity rates.