Page 191 - Saginaw FY19 Annual Budget
P. 191

CITY OF SAGINAW

                               CAPITAL IMPROVEMENT PROJECTS - WATER
                                                        2018-2022


              Old Decatur Rd 12" Water Line Phase 1
              Scope        West McLeroy Blvd to First Baptist Church
              Method       Open-cut
              Project Cost $260,000
              Fiscal Year  Future CIP
                           This project would provide additional transmission capacity along Old Decatur Rd from
              Description  Longhorn Pump Station to the Wayside Elevated Tank.  This project could be constructed by
                           developers.
              Impact on    There will be an eventual increase in maintenance costs as this is a new water line.  As the
              Operating
              Budget       infrastructure ages, estimated annual maintenance cost will be $2,501.

              Saginaw Blvd 16" Water Line Phase 2
              Scope        Palomino across Saginaw Blvd to Samson 12" water line
              Method       bore and open-cut with pavement patch
              Project Cost $1,221,050
              Fiscal Year  FY 2018-2019
                           This project will provide additional transmission capacity east of Saginaw Blvd.  This project
              Description  will connect transmission mains from Longhorn Pump Station on the west side of Saginaw
                           Blvd.
              Impact on
              Operating    There will be an eventual increase in maintenance costs as this is a new water line.  As the
                           infrastructure ages, estimated annual maintenance cost will be $2,863.
              Budget












































                                                             187
   186   187   188   189   190   191   192   193   194   195   196