CITY OF SAGINAW

                               CAPITAL IMPROVEMENT PROJECTS - WATER
                                                        2018-2022


              West McLeroy 12" Water Line Phase 2
              Scope        Elementary #14 to Old Decatur Rd
              Method       Open-cut with pavement patch
              Project Cost $280,600
              Fiscal Year  Project to begin in FY 2020-2021
                           This project would provide additional transmission capacity along W. McLeroy Blvd. from
              Description
                           Longhorn Pump Station to the Wayside Elevated Tank.
              Impact on
              Operating    There will be an eventual increase in maintenance costs as this is a new water line.  As the
                           infrastructure ages, estimated annual maintenance cost will be $2,479.
              Budget

              East McLeroy 12" Water Line
              Scope        S-Curve to FM 156 (Blue Mound Road)
              Method       Open-cut within future ROW
              Project Cost $550,000
              Fiscal Year  Future CIP
                           This project is the third phase of a three phase project to provide improved transmission
              Description  along East McLeroy Blvd between Saginaw Blvd and FM 156.  This project could be
                           constructed by developers.
              Impact on    There will be an eventual increase in maintenance costs as this is a new water line.  As the
              Operating
              Budget       infrastructure ages, estimated annual maintenance cost will be $2,788.

              Basswood Blvd 12" Water Line
              Scope        Bailey-Boswell Road to TXU Easement
              Method       Open-cut within future ROW
              Project Cost $540,000
              Fiscal Year  Future CIP
                           This project could be constructed by developers.It will provide improved transmission
              Description
                           between the Jarvis Rd. elevated tank and the east side of the City.
              Impact on    There will be an eventual increase in maintenance costs as this is a new water line.  As the
              Operating    infrastructure ages, estimated annual maintenance cost will be $2,795.
              Budget

              Old Decatur Rd 8" Water Line
              Scope        West McLeroy Blvd to Springhill Dr
              Method       Open-cut
              Project Cost $290,000
              Fiscal Year  Future CIP
                           This project provides a link between West McLeroy Blvd and Park West Subdivision.  This
              Description
                           project could be constructed by developers.
              Impact on    There will be an eventual increase in maintenance costs as this is a new water line.  As the
              Operating    infrastructure ages, estimated annual maintenance cost will be $2,556.
              Budget