                              CAPITAL IMPROVEMENT PROJECTS - STREETS
                                                        2018-2022


             Heather Ridge Parkway Extension
             Scope        400' North of Raven Dr. to Woodcrest Development
             Method       New Construction
             Project Cost $1,000,000
             Fiscal Year  Future CIP
             Description  Construction of a 2-lane undivided roadway and associated drainage improvements.
             Impact on    There will be an eventual increase in maintenance costs as this is a new roadway. As the
             Operating
             Budget       infrastructure ages, estimated annual maintenance cost will be $1,555.

             Basswood Blvd Extension
             Scope        Extend Basswood Boulevard to Bailley Boswell Road
             Method       New Construction
             Project Cost $490,000
             Fiscal Year  Construction began in FY 16/17
                          Construction from Whistle Stop Dr to Bailey Boswell Road; 2 lanes to Woodcrest Development
             Description
                          then 4 lanes to Bailey Boswell Road. City is participating with developer.
             Impact on    There will be an eventual increase in maintenance costs as this is a new roadway. As the
             Operating    infrastructure ages, estimated annual maintenance cost will be $2,842.
             Budget

             Railroad Quiet Zone Study/Implementation
             Scope        Multiple Railroad Crossings within City Limits
             Method       Study
             Project Cost $60,000
             Fiscal Year  Future CIP
             Description  Study of railroad quiet zones and implementation.
             Impact on    There will be an increase in maintenance costs for this project.  However, because this is a
             Operating    future project and the scope of the improvements is unknown, we are not able to quantify the
             Budget       impact on the operating budget for implementation of the study results at this time.