Page 196 - Saginaw FY19 Annual Budget
P. 196
CITY OF SAGINAW
CAPITAL IMPROVEMENT PROJECTS - DRAINAGE
2018-2022
Saginaw Blvd System #2 Phase 6
Scope Northern to Cambridge
Project Cost $1,600,000
Fiscal Year Future CIP
This project includes the extension of Drainage System #2 from Lemon Street to Northern Ave.
Description Design has been completed. Easements must be acquired outside the TxDOT rights-of-way.
Franchise utilities that conflict with the proposed drainage system must be relocated.
Impact on The operating impact of a closed pipe project is minimal. Upon completion of drainage
Operating improvements, there will be fewer emergency call outs during heavy rain events Estimated
Budget operating savings is $525.
Saginaw Blvd System #2 Phase 7
Scope Cambridge to Minton
Project Cost $675,000
Fiscal Year Future CIP
This project includes the extension of Drainage System #2 from Lemon Street to Northern Ave.
Description Design has been completed. Easements must be acquired outside the TxDOT rights-of-way.
Franchise utilities that conflict with the proposed drainage system must be relocated.
Impact on The operating impact of a closed pipe project is minimal. Upon completion of drainage
Operating improvements, there will be fewer emergency call outs during heavy rain events Estimated
Budget operating savings is $525.
East Cement Creek Improvements Phases 1-3
Scope Opal Street to West McLeroy Blvd with culvert at West McLeroy Blvd
Project Cost $3,395,000
Fiscal Year Future CIP design and survey to begin in FY 2018-2019
Internal drainage at Blue Ridge. Channel improvements Opal St. to Blue Ridge Trail and Blue
Description Ridge Tr. To W McLeroy Blvd. This project may need to be accelerated based on flooding
issues in East Cement Creek Drainage Basin.
Impact on The operating impact of a closed pipe project is minimal. Upon completion of drainage
Operating improvements, there will be fewer emergency call outs during heavy rain events Estimated
Budget operating savings is $1,575.
Meadow Street Ditch Improvements
Scope Channel behind homes on Meadow Dr. from Fenway Ln. to Knowles Dr.
Project Cost $675,000
Fiscal Year Future CIP
Description This project will fill in an existing grass channel and will pipe the existing flow.
Impact on The operating impact of a closed pipe project is minimal. Upon completion of drainage
Operating improvements, there will be fewer emergency call outs during heavy rain events Estimated
Budget operating savings is $525.
192