Page 288 - 2019 Budget Detail.xlsx
P. 288

Capital Request / Project Form
                     Department                             Project Title                    Project Number
                  Fire Department                      Fire Station Renovation                  19-002


               Project Description
               This project involves a multi-area remodelling project in the fire station.  The project includes replacing windows, re-
               locating plumbing and electrical in the apparatus bay, installing spray foam insulation and insulated door panels to
               bay doors, replacing doors, relocating rooms in the living quarters, and creating a secure front entrance.


               Project Justification
               The fire station was built in 1961 and was originally designed for volunteer firefighters and not 24 hour operational staffing.  We only have
               one shower in the facility and shift changes involve up to 10 personnel trying to cycle through each morning.  The water heaters are small
               capacity and were installed in 1997.  This remodel will give each employee a private bedroom and the Captains will have a room big
               enough to serve as office and bedroom.  There will be a sleepiung position for students and extra stafing purposes via installation of a
               Murphy Bed.  Our heat loss in the truck bays during the winter is extensive due to lack of weatherstripping on bay doors and lack of
               insulation.  The lighting in the truck bay will also be replaced with LED lighting that is more effective and less costly to operate.  Winter
               heating expenses should also decrease with installation of insulation.

               Project Schedule         Beginning Date      End Date   History       Fiscal Year    Amount
               Professional Services                                   CIP Budget      2019            $112,300
               Engineering/Design                                      Revision                             $0
               Land/ROW Acquisition                                    Revision                             $0
               Construction               10/1/2018         1/1/2019   TOTAL                           $112,300
               Improvements
               Vehicles
               Equipment

               Sources of Funds       Prior Yrs  18/19 Budget  19/20 Budget  21-Completion  Total
               General Obligation Bonds     $0        $0        $0             $0              $0
               Certificates of Obligation   $0        $0        $0             $0              $0
               Federal/State Grants         $0        $0        $0             $0              $0
               Drainage Fund                $0        $0        $0             $0              $0
               RHDC Fund                    $0        $0        $0             $0              $0
               HOT Fund                     $0        $0        $0             $0              $0
               General Fund                 $0   $112,500       $0             $0         $112,500
               Oil & Gas Fund               $0        $0        $0             $0              $0
               Utility Fund                 $0        $0        $0             $0              $0
               CCPD Fund                    $0        $0        $0             $0              $0
               TOTAL FUNDING                $0   $112,500       $0             $0         $112,500

               Project Costs          Prior Yrs  18/19 Budget  19/20 Budget  21-Completion  Total Cost
               Truck Bay Insulation         $0    $25,000       $0             $0          $25,000
               Bathroom Replacement         $0    $17,500       $0             $0          $17,500
               Interior Remodel             $0    $45,000       $0             $0          $45,000
               Truck Bay Lighting           $0     $2,000       $0             $0           $2,000
               Replacement Windows          $0     $5,000       $0             $0           $5,000
               Parking Lot Re-Surface       $0     $4,800       $0             $0           $4,800
               Station Access Control       $0    $13,000       $0             $0          $13,000
               TOTAL COSTS                  $0   $112,300       $0             $0         $112,300

               Operating Impact
               There will be a savings in natural gas costs for the truck bays during the winter and for warming water for the water
               heaters.  Truck bay temps should also be reduced in the summer with the new insulation making it more comfortable
               when outside work is necessary.   19-20         20-21       21-22   22-23  Total
               Fiscal Year
                                       18-19
               Amount                $112,300     $0            $0          $0      $0   $112,300
               Total Operating Impact  $112,300   $0            $0          $0      $0   $112,300


                                                            276