Schedule 5
                                            Aquatic Park Capital Projects
                                                   Budget Summary


                                                          Project To   2018/19     2019/20     2020 To
                                                            Date       Adopted    Estimated   Completion    Total

       Project Costs
       Continuing Projects
       WP1801  General Facility Improvements (2018)            100,000         0          0          0 $     100,000
       WP1802  Main Filtration Replacement                     600,000         0          0          0 $     600,000
       Total Continuing Projects                         $     700,000 $       0 $        0 $        0 $     700,000
       New Projects
       WP1901  General Facility Improvements (2019)                0      100,000         0          0 $     100,000
       Total New Projects                                $         0 $    100,000 $       0 $        0 $     100,000

       Total Project Costs                               $     700,000 $  100,000 $       0 $        0 $     800,000

       Funding Sources
       Certificates of Obligation                              600,000         0          0          0  $    600,000
       Reserves                                                100,000    100,000         0          0  $    200,000
       Total Sources of Funds                            $     700,000 $  100,000 $       0 $        0 $     800,000