Summary of Project Expenditures
                                       2018/2019 Capital Improvement Program


                                               Project To     Adopted       Estimated      2020 to         Total
        Program Classification                   Date         2018/2019     2019/2020     Completion   Expenditures

        Street & Sidewalk                       42,810,484      2,865,000            0              0  $  45,675,484

        Drainage                                 1,904,108       230,000             0              0  $   2,134,108
        Utility                                 12,281,525      1,755,000            0              0  $  14,036,525

        Parks & Recreation                       9,475,901       658,000        811,000             0  $  10,944,901

        Aquatic Park                               700,000       100,000             0              0  $    800,000
        Facilities                              69,465,087       212,000             0              0  $  69,677,087

        Major Capital Equipment                  5,361,257      4,441,500        98,000             0  $   9,900,757

        Economic Development                    15,627,826       750,000             0              0  $  16,377,826
        CIP Personnel                              330,004       336,657             0              0  $    666,661

        Other                                      528,343        94,000             0              0  $    622,343

        Total CIP Project Expenditures       $  158,484,535  $  11,442,157  $   909,000  $          0  $  170,835,692


















































                                                             448