DRAINAGE BOND FUND
FUNDED PROJECTS
Project Description Project Justification Status 09/30/18 Operating Impact 9/30/18
This project will widen Pipeline Road from This project is necessary to improve traffic flow along Pipeline Construction began during the O&M impact due to reduced
Precinct Line Road to Hurstview Drive. Many Road. This project will include the results of the redevelopment 2016-2017 budget year and is maintenance costs with
of the intersections have been widened in efforts and zoning overlay for the area east of Precinct Line estimated to be complete construction of new street.
preparation for this project. Road. Tarrant County has pledged to participate in 50% of the somtime during fiscal year 2018-
construction cost. 2019.
This project consists of lining an existing This project is currently in the TBD
corrugated metal storm drain pipe with a cast- This project will repair some corroded spots in the flow line of planning phase.
in-place pipe material. Some access to the the arch pipe and extend the life for another 50 years plus.
pipe will be required to install the lining. This drainage pipe is carrying considerable rainfall runoff from
the residential and commercial areas to the north and west of
the State Highway 26 / Grapevine Highway and Hurst view /
Norwood Drive intersection. Maintaining this storm drain is
critical for the commercial/retail property on Grapevine
Highway in this area.
This project consists of repairs to joints, This project is necessary to improve traffic flow along Pipeline This project is currently in the TBD
substructure point repairs, spalled surface Road. This project will include the results of the redevelopment planning phase.
concrete, and the concrete railings. efforts and zoning overlay for the area east of Precinct Line
Road. Tarrant County has pledged to participate in 50% of the
construction cost.
515