DRAINAGE BOND FUND
                                                      FUNDED PROJECTS
                                                                                                 Annual
                   Project Number,               Estimated   Actual
                   Description &                   Cost   Expenditures as   Expenditures for 2018-  Expenditures for   Operations &
                                                                         2019
                                                                                                Maintenance
                                                                                    2019-2020
                   Date Introduced in CIP         Budget   of 10/01/18
                                                                                               Impact (Savings)
                   Project 6304105
                   Pipeline Phase 2                 $11,823    $11,823         $0          $0       ($15,000)
                   10/30/09


                   Project 6419301
                   Norwood North Drainage           $95,000       $0        $57,000     $38,000        TBD
                   10/30/18




                   Project 6419302
                   Bedford Court W Bridge          $100,000       $0        $60,000     $40,000        TBD
                   10/30/18

                   TOTAL                            $206,823   $11,823      $117,000     $78,000    ($15,000)