Fiscal Year 2019 Capital Plan

             The  total  of  the  capital  projects  planned  in  the  Capital  Projects  Funds  for  FY2019  is
             $23,126,000.   The Budget Summary of the Capital Projects Funds is listed below:

                                                 Actual         Adopted         Projected         Adopted
             Capital Project Funds               FY2017          FY2018          FY2018           FY2019
             Street Reconstruction             $4,204,910       $6,897,500      $1,831,070       $8,083,500
             Capital Improvements                    736,186       1,595,000        1,434,000         8,375,000
             Equipment Replacement                   591,444          542,100       1,052,100            573,000
             Water & Sewer Projects                  905,411     12,247,500         9,728,416         4,799,500
             Water & Sewer Impact Fees              19,408            250,000            75,000           250,000
             Drainage Capital Projects                 50,885          500,000          425,000        1,045,000
                       Total Revenues          $6,508,243     $22,032,100 $14,545,586           $23,126,000

             A matrix of the FY2019 expenditures is listed below:

                                    Vehicles /                                  Water &
             Fund                   Equipment    Streets  Fire Station  Parks    Sewer     Drainage     Total
             Street Reconstruction         $0 $8,083,500         $0        $0         $0         $0   $8,083,500

             Capital Improvements                 -               -    5,500,000    2,875,000               -                -       8,375,000
             Equipment Replacement        573,000              -               -               -                -                -          573,000
             Water & Sewer Projects               -               -               -               -     4,799,500               -       4,799,500
             Water & Sewer Impact Fees              -               -               -               -        250,000               -          250,000
             Drainage Capital Projects               -               -               -               -                -     1,045,000      1,045,000
                       Total          $573,000 $8,083,500 $5,500,000 $2,875,000 $5,049,500 $1,045,000 $23,126,000


             Capital Expenditures and Impact on Operating Costs

             Most  of  the  capital  improvement  projects  are  recurring  (reconstruction/replacement)
             expenditures since the City is a matured city with aged streets, water and sewer systems.  The
             City rarely adds new roads and or new infrastructure for expansion.  Most of the reconstruction
             expenditures on capital project do not have significant impact on operating cost.

             For  non-recurring  (expansion)  capital  outlays,  the  impact  upon  operations  of  these
             improvements is reflected in the  additional cost of maintaining  parks, streets and drainage
             systems.

             Replacement  of  storm  sewers,  curb  and  gutters  does  not  reduce  the  annual  budget  for
             maintenance.  It does allow these scarce dollars to be allocated to other projects for up to 15
             years.  Every mile of road in which the City rebuilds the storm sewers, curb and gutter allows
             the City to shift nearly $40,000 in maintenance materials and labor to other needed projects.
             Replacing worn and damaged water lines reduces lost water and increases customer billing.
             Each 1% of lost water that is captured through capital outlay is worth about $90,000 at current