                            Project                     Performance Measure(s)      City Service Team (Department)
             Core   Advanced Metering Infrastructure   Install 9,000 meters and MIUs in FY   Strategic Support (Water)
             INF                                   2018
             2.1.1
             Summary:
                                                                      Milestone         Estimated      Actual
             The City of Arlington Water Utilities will install 9,000                   Completion   Completion
             meters and MIU’s in 2017 through an ongoing meter   Wrap up FY 2017 Installs   Sept. 2017   Sept. 2017
             replacement program and water line renewals.       Begin MUI/Meter Installs   Oct. 2017   Oct. 2017
                                                                Council Approval of    Feb. 2018    Feb. 2018
             The MIU receives input from the meter register and   Meter Replacement
             remotely sends data to a fixed base data collector, located   funding
             at one of five elevated storage tanks around the City. Top   Council Approval of   Sept. 2018   Sept. 2018
             of the hour readings and other diagnostics are instantly   Annual Meter Supply
             forwarded to the network allowing for a greater awareness   Contract
             of the distribution system and possible on property leak   Complete MIU/Meter   Sept. 2018   Sept. 2018
             conditions.  In addition, the MIU stores up to 35 days of   Installation for FY 2018
             hourly consumption, providing the utility with the ability to
             extract detailed usage profiles for consumer education,
             such as water conservation, and billing dispute resolution.

             Update:
             A total of 8,463 MIUs were installed during FY 2018.

                                                    Infrastructure

                          Goal 2: Support and Expand Programs to Reduce Environmental Impacts
                                   Objective 1: Mitigate Operating Costs and Impact on Environment
                            Project                    Performance Measure(s)       City Service Team (Department)
             Core   Water Conservation Program     Maintain metered ratio rolling   Strategic Support (Water)
             INF                                   average above 88%
             2.1.2
             Summary:
                                                                              Metered Ratio
             The City of Arlington Water Utilities will maintain a   100%
             metered ratio rolling average above 88%.  In FY   90%
             2018, Arlington Water Utilities will proactively   80%
             evaluate 25,000 linear feet of water line for leaks to   70%
             catch them in the early stages before significant   60%
             water loss occurs.  Arlington Water Utilities will also   50%
             evaluate and make recommendations to purchase    40%
             additional leak detection technologies to accomplish   30%
             this goal.                                       20%
                                                              10%
             Update:                                           0%
                 th
             The 4  quarter ended with a 13‐month rolling           FY 2018 1st Qtr  2nd Qtr 3rd Qtr  4th Qtr
             average of 89.95% metered ratio.