Infrastructure
Goal 1: Plan, Manage, and Maintain Public Assets
Objective 3: Maintain City Standards for all Municipal Buildings
Project Performance Measure(s) City Service Team (Department)
Core Construct an Airport Equipment Total Aircraft Operations Economic Development and
INF Storage Facility and Public Capital Investment (Aviation)
1.3.1 Restroom
Summary: Update:
The demolition of two rows of hangars has left the Airport Construction is complete. The public restroom is open and
without proper storage for its mowing and snow and ice available for tenant’s use. Airport Operations personnel
control equipment. The Airport is also without a public have relocated the equipment out of the T‐hangars that
restroom in close proximity to the remaining T‐hangars. were formerly used for storage. Those hangars have been
City Council approved $400,000 for construction of an leased to aircraft owners.
equipment storage facility and a public restroom in the
2017 Capital Budget.
Maintenance Building/Public Restroom
Design
Approval of Guaranteed
Maximum Price
Plan Review
Construction Contract
Preparation
Construction
Certificate of Occupancy
Equipment Relocation
7/17 10/17 1/18 4/18 7/18 10/18