CITY OF KELLER FIVE-YEAR CAPITAL IMPROVEMENTS PROGRAM (CIP) SUMMARY



                                                           FISCAL YEARS
                                                                                                          TOTAL ALL
             PROJECT     PRIOR YEARS  FY 2024-25  FY 2025-26  FY 2026-27  FY 2027-28  FY 2028-29  FY 2029-30
                                                                                                           YEARS

                                                     WATER SYSTEM


                                                     Pearson Pump Repair
          Water-Wastewater
               Fund                              450,000               500,000                            $          950,000
          TOTAL PROJECT   $                      -   $         450,000   $          500,000   $                    -   $                    -   $                     -   $                     -   $          950,000
                         This project is relocated existing water lines and minimal operating impact is anticipated.



                                                Keller-Smithfield Tank Maintenance
          Water-Wastewater                                   750,000                                      $          750,000
               Fund
          TOTAL PROJECT   $                      -   $                     -   $          750,000   $                    -   $                    -   $                     -   $                     -   $          750,000
                         This project is relocated existing water lines and minimal operating impact is anticipated.


                                                    Knox Tank Maintenance
          Water-Wastewater
               Fund                                                    750,000                            $          750,000
          TOTAL PROJECT   $                      -   $                     -   $                      -   $        750,000   $                    -   $                     -   $                     -   $          750,000
           IMPACT ON O&M  This project is relocated existing water lines and minimal operating impact is anticipated.



           TOTAL  WATER    $     27,520,599   $         104,897   $       1,450,000   $        950,000   $     5,200,000   $      3,700,000   $      4,700,000   $     43,625,496