CITY OF KELLER FIVE-YEAR CAPITAL IMPROVEMENTS PROGRAM (CIP) SUMMARY
FISCAL YEARS
TOTAL ALL
PROJECT PRIOR YEARS FY 2024-25 FY 2025-26 FY 2026-27 FY 2027-28 FY 2028-29 FY 2029-30
YEARS
WATER SYSTEM
2017 SWIFT Projects
Debt Issuance 4,000,000 $ 4,000,000
Water-Wastewater
Fund 532,439 $ 532,439
TOTAL PROJECT $ 4,532,439 $ - $ - $ - $ - $ - $ - $ 4,532,439
The project replaces existing water lines and the operating impact relates to the average annual debt payment.
IMPACT ON O&M
$ 295,668 $ 297,872 $ 299,832 $ 296,450 $ 297,675 $ 298,307
Annual Water Line Replacements
Water-Wastewater
Fund 1,073,772 400,000 200,000 200,000 200,000 200,000 200,000 $ 2,473,772
Other 455,187 $ 455,187
TOTAL PROJECT $ 1,528,959 $ 400,000 $ 200,000 $ 200,000 $ 200,000 $ 200,000 $ 200,000 $ 2,928,959
IMPACT ON O&M The project replaces existing water lines and minimal operating impact is anticipated.
Tank Maintenance
Water-Wastewater
Fund 1,650,000 175,000 $ 1,825,000
Other 4,500,000 $ 4,500,000
TOTAL PROJECT $ 6,150,000 $ 175,000 $ - $ - $ - $ - $ - $ 6,325,000
IMPACT ON O&M The project provides capital maintenance of water tanks and minimal operating impact is anticipated.
2021 SWIFT
Debt Issuance 4,060,000 $ 4,060,000
Water-Wastewater 251,390 $ 251,390
Fund
TOTAL PROJECT $ 4,311,390 $ - $ - $ - $ - $ - $ - $ 4,311,390
The project replaces existing water lines and the operating impact relates to the average annual debt payment.
IMPACT ON O&M
$ 289,380 $ 288,823 $ 288,081 $ 287,061 $ 290,776 $ 289,237
2023 SWIFT
Debt Issuance 4,060,000 $ 4,060,000
Water-Wastewater 250,000 250,000 $ 500,000
Fund
TOTAL PROJECT $ 4,310,000 $ 250,000 $ - $ - $ - $ - $ - $ 4,560,000
The project replaces existing water lines and the operating impact relates to the average annual debt payment.
IMPACT ON O&M
$ 334,041 $ 336,034 $ 339,526 $ 337,979 $ 336,409 $ 334,717
330