Page 333 - CityofKellerFY26AdoptedBudget
P. 333
CITY OF KELLER FIVE-YEAR CAPITAL IMPROVEMENTS PROGRAM (CIP) SUMMARY
FISCAL YEARS
TOTAL ALL
PROJECT PRIOR YEARS FY 2024-25 FY 2025-26 FY 2026-27 FY 2027-28 FY 2028-29 FY 2029-30
YEARS
WATER SYSTEM
Material Storage
Water-Wastewater
Fund 450,000 $ 450,000
TOTAL PROJECT $ - $ 450,000 $ - $ - $ - $ - $ - $ 450,000
IMPACT ON O&M The project is capital maintenance of an existing facility and minimal operating impact is anticipated.
30" Transmission Line Replacement
Debt Issuance - $ -
TOTAL PROJECT $ - $ - $ - $ - $ - $ - $ - $ -
The project is capital maintenance of an existing facility and the operating impact relates to the average annual debt payment.
IMPACT ON O&M
Pump Station Rehab
Debt Issuance 4,500,000 $ 4,500,000
TOTAL PROJECT $ - $ - $ - $ - $ - $ - $ 4,500,000 $ 4,500,000
The project is capital maintenance of an existing facility and the operating impact relates to the average annual debt payment.
IMPACT ON O&M
$419,012.00
SCADA Maintenance
Water-Wastewater 540,000 $ 540,000
Fund
TOTAL PROJECT $ 540,000 $ - $ - $ - $ - $ - $ - $ 540,000
IMPACT ON O&M The project is capital replacement of an existing equipment and minimal operating impact is anticipated.
Knox Tank Mixer
Water-Wastewater 302,998 $ 302,998
Fund
TOTAL PROJECT $ 302,998 $ - $ - $ - $ - $ - $ - $ 302,998
IMPACT ON O&M The project is capital maintenance of an existing facility and minimal operating impact is anticipated.
Pearson Pump Station Generator
Other 2,500,000 $ 2,500,000
TOTAL PROJECT $ 2,500,000 $ - $ - $ - $ - $ - $ - $ 2,500,000
IMPACT ON O&M The project is capital maintenance of an existing facility and minimal operating impact is anticipated.
331