Page 458 - CityofEulessFY26AdoptedBudgetOrdinance2432
P. 458

City of Euless

                                            Capital Project Request


           Department:            PUBLIC  WORKS                                Date  Prepared:       May 31, 2019
           Submitted By:          HAL  CRANOR                                  Date  Completed:     May 31,  2025
           Project  Title:        FY2024 STREET IMPROVEMENTS
           Project  Type:         STREET                      Sub - Type:   IMPROVEMENTS

           Project Code:          PS2401                      Priority:   A
           COUNCIL  AUTHORIZATION:













           RELATIONSHIP   TO OTHER   PROJECTS   AND/ OR  MASTER   PLAN:












           PROJECT   DESCRIPTION:
           The project consists of edge milling,  asphalt overlay, and restriping on various streets prioritized by pavement
            condition  index  of the roadways.










           PROJECT SCHEDULE:
            Began  Construction:   October  2023
            Construction  Complete:   September  2024








           JUSTIFICATION:
           The existing asphalt pavement is deteriorating.   The asphalt overlay will provide an improved  riding surface,
            extend the life of the roadway,  and enhance the appearance of the streets.











                Ordinance No.  2432,  Page 452 of 474