                                            Capital Project Request


           Department:            PUBLIC  WORKS                                Date  Prepared:       July 09,2024
           Submitted By:          MAJOR  JONES                                 Date  Completed:     May 31,  2025
           Project  Title:        FY2025 DRAINAGE   CURB &  GUTTER IMPROVEMENTS
           Project  Type:         DRAINAGE                    Sub - Type:   IMPROVEMENTS

           Project Code:          DR2502                      Priority:   A
           COUNCIL  AUTHORIZATION:













           RELATIONSHIP   TO OTHER   PROJECTS   AND/ OR  MASTER   PLAN:












           PROJECT   DESCRIPTION:
           The project consists of the removal and replacement of damaged curb and gutter throughout the City.











           PROJECT SCHEDULE:
            Began  Construction:   October  2024
            Construction Complete:  May 2025








           JUSTIFICATION:
           The existing curb and gutter along many City streets has aged,  failed,  or been damaged.  The curb and gutter
            serves as part of the City's storm water collection system.  The new curb and gutter will improve drainage
            performance while also enhancing the appearance of City streets.