Page 212 - CityofEulessFY26AdoptedBudgetOrdinance2432
P. 212

City of Euless

                                            Capital Project Request


                                                                                                    April  29, 2022
           Department:            PUBLIC  WORKS                                Date  Prepared:
           Submitted By:          HAL  CRANOR                                  Date  Completed:
           Project  Title:        LINE  REPLACEMENT —   TRAILWOOD   ADDITION
           Project  Type:         WASTEWATER                  Sub - Type:   MAIN  REPLACEMENT

           Project Code:          WW2304                      Priority:   A
           COUNCIL  AUTHORIZATION:
            November 22,  2022:  Authorized  the City Manager to negotiate  and execute an engineering  services contract
           with Plummer Associates,  Inc.  for the design of the FY2023 Sanitary Sewer Rehabilitation  Project.
            May 14,  2024:  Awarded  Bid No.  018- 23 for the FY2023 Sanitary Sewer Rehabilitation  Project to Douglas Dailey
            Construction,  LLC for the replacement  of sanitary sewer mains located in the Trailwood  Addition and authorized
           the City Manager to enter into a contract with Douglas Dailey Construction,  LLC.





           RELATIONSHIP   TO OTHER   PROJECTS   AND/ OR  MASTER   PLAN:
           The wastewater  mains included in this project are part of the City' s Wastewater  System Master Plan.










           PROJECT   DESCRIPTION:
           The project consists of the replacement of wastewater mains in the Trailwood Addition including those along
           Trailwood Drive,  Cripple Creek Drive,  Shenandoah Drive,  Timberlane Terrace,  Summit Ridge Drive,  and Shadow
            Lane.  See project map for additional  details on specific line locations.








           PROJECT SCHEDULE:
            Began  Design:   December  2022
            Design  Complete:   March  2024
            Began Construction:  July 2024
           Anticipate Construction Complete:  July 2025





           JUSTIFICATION:
            Many wastewater mains throughout the City are 50+  years old.  Most of these lines are clay tile and are
            susceptible to ground movement,  pulled joints, root infiltration,  and deterioration from hydrogen sulfide gas.
            Many are substandard in size and have inflow/ infiltration problems.  This project is part of the systematic
            replacement of wastewater mains using a worst -first approach to reduce maintenance costs and customer
            problems.






                Ordinance No.  2432,  Page 206 of 474
                                                             52
   207   208   209   210   211   212   213   214   215   216   217