                           Water and Sewer Capital Projects Fund Descriptions

               1.   Walnut Creek Lift Station Upgrade

                    This project consists of the upgrade of the existing Walnut Creek Lift Station.  The existing lift station
                    is near capacity.  The upgrade will allow for future development in the area.

                    Cost:                     $900,000

                    Funding Source:           Excess Bond Reserve Funds
                                              Sewer Impact Fees

                    Operating Budget Impact:   No direct  financial impact  on the operating budget  is expected as a
                                              result of this project.  No additional staff will be required as a third-party
                                              contractor will be hired to perform the labor.  Current staff members will
                                              be involved with the project and they must dedicate time to oversee the
                                              project which does take staff time away from routine duties creating an
                                              indirect impact on the operating budget.

                    Department:               Administration
                                              Utility Maintenance

               2.   Walnut Creek Force Main Upgrade

                    This project consists of the upgrade of the existing  sewer force main from the Walnut Creek Lift
                    Station to the Ash Creek Wastewater Treatment Plant.  This project will be performed in conjunction
                    with the Walnut Creek Lift Station Upgrade project and will allow for future development in the area.

                    Cost:                     $1,500,000

                    Funding Source:           Utility Fund Transfer
                                              Sewer Impact Fees

                    Operating Budget Impact:   No direct  financial impact  on the operating budget  is expected as a
                                              result of this project.  No additional staff will be required as a third-party
                                              contractor will be hired to perform the labor.  Current staff members will
                                              be involved with the project and they must dedicate time to oversee the
                                              project which does take staff time away from routine duties creating an
                                              indirect impact on the operating budget.

                    Department:               Administration
                                              Utility Maintenance


               3.   Avondale Lift Station Upgrade CDBG Project

                    This project consists of the upgrade of an existing lift station in the  Avondale  Avenue area.   The
                    existing lift station  is near capacity.  The  upgrade will allow for future  development in the  area to
                    connect to the City’s wastewater system.  The project was proposed and approved to be included in
                    the Tarrant County Community Development  Block Grant (CDBG) program  and will be partially
                    funded by the grant.

                    Cost:                     $50,000 (City’s portion)