            PURPOSE STATEMENT:
            To provide potable and palatable water in sufficient quantities and pressure for domestic use and for fire fighting
            purposes at a reasonable cost.







            GOALS AND OBJECTIVES:
            Continue to improve the appearance of the water plant
            Continue to improve the efficiency of the production system and reduce operating cost per 1,000 gallons
            Continue to upgrade chlorination system to become more automated
            Continue replacing antiquated actuators and valves that are beginning to show signs of failure
            Construct new chemical injection building at the City's Lake Lot property
            Add Chlorine residual monitoring devices and chemical metering pumps to the Plant's SCADA system
            Upgrade High Service Pump #4 to operate on a Variable Frequency Drive motor controller
            Upgrade online turbidity monitoring devices
            Replace Unit #1028 Motor Vehicle
            Extend community awareness educational tools and outreach promoting the Water Plant and Conservation




            KEY POINTS OF PROPOSED BUDGET:
            Personnel:  Increase due to impact of FY 24 step increases, pay plan market adjustment, and increased
                benefits costs.
            Supplies:  Increase due to the rising cost of treatment process chemicals, fuel, and minor equipment purchases.
            Services:  Increase for additional mandated testing, generator maintenance agreements, and raw water
                purchases.











            KEY INDICATORS OF PERFORMANCE:                                       FY 22-23   FY 23-24  FY 24-25
                                                                                   Actual   Estimate  Projection
            Increase plant reuse water by 1.5%                                    1.15%      1.50%     1.50%
            Decrease in Utility Cost per MG (Goal to reduce by 1%)                -1.9%      1.0%       1.0%
            Compliance with Federal and State regulatory requirements             100%       100%      100%
            100% of Bacteriological samples testing negative                      100%       100%      100%
            Raw Water Total (MG)                                                   699        720       755
            Treated Water Total (MG)                                               679        700       725
            In-house Lab Samples Performed                                        58,671     62,000    65,000





           City of Azle FY 2024-2025 Budget                                                                    144