Page 321 - Euless ORD 2360 Adopted FY 23-24 Budget
P. 321

PROJECT TITLE:  KIDDIE CARR PARK IMPROVEMENTS                              PROJECT CODE:  PR2307

           NET EFFECTS ON OPERATING      AND                    TOTAL  ESTIMATED   CAPITAL  COST:
           MAINTENANCE    COST (+   OR -)  ANNUAL:

           Direct Operatina Cost                                Demolition $                               5, 500

           Personnel:       Full Time                           Site work $                              155, 000
                            Part Time $                       0 Hardscape $                              322, 000
           Total Salary $                                     0 Landscape $                               60, 500
           Purchase of Services                                 Fixtures/  Furnishings $                  92, 000

           Materials &  Supplies                                Development/ Prof.  Services $           254, 000
           Utilities                                            TDLR $                                     1, 500
                                                                Geotech $                                  3, 000




                                                              0
           Subtotal: $                                        0 Total Estimated Capital Cost $           893, 500

           Maintenance  Costs                                   Funding Source:
                                                                Transfer  from:
                                                                EDC Operating Fund $                     893, 500


                                                              0

           Subtotal: $                                        0
                                                                Transfer to:
                                                                EDC CIP Fund Balance ($                 893, 500)
           Total Estimated Annual Cost $                      0 Total Funding $                                0
                                                   CURRENT     STATUS
                                                                               OVER/ UNDER
           PHASE/ FUNDING  SOURCE                      BUDGET      EXPENDED     BUDGET (-+)           EXPENDED
          Development/ Professional  Services           254, 000            0       254, 000                0%
          Construction                                  547, 500            0       547, 500                0%
          Park  Furnishings                              92, 000            0         92, 000               0%


















           TOTAL  PROJECT $                             893, 500 $          0 $     893, 500                0%



                Ordinance No.  2360,  Page 321 of 326