Page 324 - Euless ORD 2360 Adopted FY 23-24 Budget
P. 324

City of Euless

                                            Capital Project Request


           Department:            COMMUNITY    SERVICES                        Date  Prepared:       May 14, 2021
           Submitted By:          RAY  MCDONALD                                Date Completed:      May 31,  2023
           Project  Title:        TRAIL LIGHTING — HERITAGE AVENUE TO BOB EDEN PARK
           Project  Type:         PARK/ RECREATION            Sub - Type:   PARK IMPROVEMENTS

           Project Code:          PR2310                      Priority:   A
           COUNCIL  AUTHORIZATION:
            October 25,  2022:  Authorized the purchase and installation of solar LED path and area lighting for a portion
           of the Trails of Euless extending from Heritage Avenue to Euless Main Street,  as well as within Bob Eden Park
           from Facility Solutions Group.  The estimated expenditure is $ 222,475 and will be paid from PR2311 and
            PR2310.







           RELATIONSHIP   TO OTHER PROJECTS AND/ OR MASTER PLAN:
           Trail -related improvements  were included in the Needs Assessment and Identification  section of the adopted
            Parks  Master  Plan.









           PROJECT   DESCRIPTION:
            Project scope consists of the installation of low level lighting along the trail from Heritage Avenue to Bob Eden
            Park.










           PROJECT SCHEDULE:
            Began Construction:  February 2023
            Construction  Complete:   April  2023








           JUSTIFICATION:
           The City of Euless has experienced significant progress in the last few years in the area of trail development with
            an extensive network of paved and unpaved trails.  The trails system is a valuable asset to the community as it
            provides a safe means for non -vehicular travel,  and also provides an opportunity for a variety of unstructured,
            low -impact recreational pursuits.  The addition of well -placed trail lighting that is frequently maintained improves
           visibility,  increases trail access, and provides convenience for trail users.  The development and maintenance of
           the trails system continues to receive significant support from the citizens as indicated in the responses to the
            needs assessment survey conducted as a part of the Parks Master Plan update.