Page 324 - Euless ORD 2360 Adopted FY 23-24 Budget
P. 324
City of Euless
Capital Project Request
Department: COMMUNITY SERVICES Date Prepared: May 14, 2021
Submitted By: RAY MCDONALD Date Completed: May 31, 2023
Project Title: TRAIL LIGHTING — HERITAGE AVENUE TO BOB EDEN PARK
Project Type: PARK/ RECREATION Sub - Type: PARK IMPROVEMENTS
Project Code: PR2310 Priority: A
COUNCIL AUTHORIZATION:
October 25, 2022: Authorized the purchase and installation of solar LED path and area lighting for a portion
of the Trails of Euless extending from Heritage Avenue to Euless Main Street, as well as within Bob Eden Park
from Facility Solutions Group. The estimated expenditure is $ 222,475 and will be paid from PR2311 and
PR2310.
RELATIONSHIP TO OTHER PROJECTS AND/ OR MASTER PLAN:
Trail -related improvements were included in the Needs Assessment and Identification section of the adopted
Parks Master Plan.
PROJECT DESCRIPTION:
Project scope consists of the installation of low level lighting along the trail from Heritage Avenue to Bob Eden
Park.
PROJECT SCHEDULE:
Began Construction: February 2023
Construction Complete: April 2023
JUSTIFICATION:
The City of Euless has experienced significant progress in the last few years in the area of trail development with
an extensive network of paved and unpaved trails. The trails system is a valuable asset to the community as it
provides a safe means for non -vehicular travel, and also provides an opportunity for a variety of unstructured,
low -impact recreational pursuits. The addition of well -placed trail lighting that is frequently maintained improves
visibility, increases trail access, and provides convenience for trail users. The development and maintenance of
the trails system continues to receive significant support from the citizens as indicated in the responses to the
needs assessment survey conducted as a part of the Parks Master Plan update.
Ordinance No. 2360, Page 324 of 326