Page 229 - Euless ORD 2360 Adopted FY 23-24 Budget
P. 229
PROJECT TITLE: 51ST CDBG LINE REPLACEMENT — FAIR OAKS BLVD/ SHELMAR DRIVE
NET EFFECTS ON OPERATING AND TOTAL ESTIMATED CAPITAL COST:
MAINTENANCE COST (+ OR -) ANNUAL:
Direct Operatina Cost Engineering 43, 000
Construction
Personnel: Full Time 300, 000
Part Time 0
Total Salary 0
Purchase of Services
Materials & Supplies
Utilities 0
Subtotal: 0
Maintenance Costs
0
0
Subtotal:
Total Estimated Annual Cost 0 Total Estimated Capital Cost 343, 000
PROPOSED METHOD OF FINANCE: CURRENT STATUS:
Operating Fund Conceptual Design % 0%
Fund Balance Preliminary Design % 0%
Special Project Fund Final Plans % 0%
Certificate of Obligation Specifications % 0%
XX 0%
County, State, Federal Funding Construction %
General Obligation Bonds
Revenue Bonds
Donations
Supplemental Sales Tax
Car Rental Tax Fund
To Be Determined
ADDITIONAL COMMENTS:
Project is contingent upon actual CDBG funding availability.
Ordinance No. 2360, Page 229 of 326
165