                                             Capital Project Request



           Department:    PUBLIC  WORKS                                    Date  Prepared:   March  30, 2023
           Submitted  By:   MAJOR JONES                                    Date Completed:
           Project  Title:   LINE  REPLACEMENT —  OAKWOOD TERRACE    NORTH PHASE III
                          WASTEWATER
           Project  Type:                               Sub -Type:  MAIN REPLACEMENT
                                                                     B
           Project  Code:                               Priority:
           RELATIONSHIP   TO OTHER   PROJECTS   AND/ OR  MASTER   PLAN:
           The wastewater mains included in this project are part of the City' s Wastewater System Master Plan.














           PROJECT   DESCRIPTION:
           The project consists of the replacement of the wastewater mains between Tyler Avenue and Marlene Drive from
           Eastcliff Drive to Commerce Street.










           PROJECT   SCHEDULE:
           FY2027







           JUSTIFICATION:
           Many wastewater mains throughout the City are 50+  years old.  Most of these lines are clay tile and are susceptible to
           ground movement,  pulled joints,  root infiltration,  and deterioration from hydrogen sulfide gas.  Many are substandard
           in size and have inflow/ infiltration problems.  This project is part of the systematic replacement of wastewater mains
           using a worst -first approach to reduce maintenance costs and customer problems.