Page 472 - Southlake FY22 Budget
P. 472

CAPITAL IMPROVEMENTS  PROGRAM (CIP)

                                                                                PArKS



                                   City of Southlake FY 2022 CIP Project Status Form

                                           Liberty Park at Sheltonwood Improvements

               DEPARTMENT: Community Services
               PROJECT
               LOCATION:  Liberty Park at Sheltonwood

               PROJECT TIMELINE: TBD     to
               DESCRIPTION:
               Funding is planned for the design and development of improvements at Liberty Park at
               Sheltonwood as per the as per the adopted Southlake 2035 Parks, Recreation & Open
               Space Master Plan. The project scope includes: water well for pond, park amenities,
               playground, expand parking, trail connectivity and improvements, volleyball court
               improvements, park and educational signage, expand existing pond, exercise stations
               along trail, trail distance markers, and pedestrian corridor from parking to center of the
               park.





                                                                        New Request     Continuation Project  Partnership
               JUSTIFICATION:                                          Mandated /    Replacement / Major   Community
                                                                       Public Health /   Rehab or Protection      Need / Service
               Design and development of improvements at Liberty Park at Sheltonwood as per the  Safety  of Capital Stock  Enhancement
               adopted Southlake 2035 Parks, Recreation & Open Space Master Plan.
                                                                        2030/2035 COMPREHENSIVE PLAN? If yes, include ref:
                                                                        Southlake 2035 Parks, Recreation & Open Space Master Plan
               ALTERNATIVES / IMPACTS IF PROJECT IS NOT FUNDED:         COMPANION PROJECT? If yes, please explain:
               Delay completion of 2nd Phase of park development.
                                                                        REVENUE GENERATING? If yes, please explain:
               STRATEGIC FOCUS AREA: Quality Development & Infrastructure
               PROJECT #:  2022-62
                                                        EXPENDITURE SCHEDULE
                CAPITAL PROJECT COSTS  TOTAL PRIOR  2022  2023     2024    2025      2026    UNFUNDED    TOTAL
                  PLANNING / FEASIBILITY STUDY                                                             0
                 ENGINEERING & DESIGN; TESTING                                                268,200    268,200
                     LAND & ROW ACQUISITION                                                                0
               LANDSCAPING,  ART,  URBAN  DESIGN                                                           0
                          CONSTRUCTION                                                       2,233,800  2,233,800
                          CONTINGENCY                                                         298,000    298,000
                              TOTAL    0         0        0        0        0         0      2,800,000  2,800,000
                                                         OPERATIONAL IMPACT
               OPERATIONAL PROJECT COSTS  TOTAL PRIOR  2022  2023  2024    2025      2026    UNFUNDED    TOTAL
                       MAINTENANCE COSTS                                                      20,000     20,000
                        PERSONNEL COSTS                                                                    0
                              TOTAL    0         0        0        0        0         0       20,000     20,000
                                                          FUNDING SCHEDULE
                 CAPITAL FUNDING SOURCE  TOTAL PRIOR  2022  2023   2024    2025      2026    UNFUNDED    TOTAL
                          GENERAL FUND                                                                     0
                               CEDC                                                                        0
                               CCPD                                                                        0
                   PARK DEDICATION FEE FUND                                                                0
                         PUBLIC ART FUND                                                                   0
                   ROADWAY IMPACT FEE FUND                                                                 0
                  SANITARY SEWER IMPACT FEE                                                                0
                               SPDC                                                          2,800,000  2,800,000
               STORMWATER UTILITY SYSTEM FUND                                                              0
                              TIRZ #1                                                                      0
                           UTILITY FUND                                                                    0
                     WATER IMPACT FEE FUND                                                                 0
                              TOTAL    0         0        0        0        0         0      2,800,000  2,800,000
               CCPD: CRIME CONTROL & PREVENTION DISTRICT                                SPDC: SOUTHLAKE PARKS DEVELOPMENT CORPORATION
                CEDC: COMMUNITY ENHANCEMENT & DEVELOPMENT CORPORATION                      TIRZ #1:  TAX INCREMENT REINVESTMENT ZONE #1
                                                                           BUDGET BOOK   |  FY 2022 City of Southlake  471