Page 388 - Southlake FY22 Budget
P. 388

CAPITAL IMPROVEMENTS  PROGRAM (CIP)

                                                                             MOBILITY



                           Funding   Total Prior
             Project number                      FY 2022   FY 2023  FY 2024   FY 2025   FY 2026   Beyond     Total
                           Source     Funding
            FM 1709
            Deceleration   Funding is requested to design and construct deceleration lanes along East Southlake Boulevard at Byron Nelson Parkway and
            Lanes at Byron  West Southlake Boulevard at Southridge Lakes Parkway. This project includes landscaping modifications.  Will seek potential
            Nelson and    funding partnership with the North Central Texas Council of Governments (NCTCOG).
            Southridge Lakes

                          General
            2022-06                    $1,000,000  $200,000      $0       $0        $0        $0        $0   $1,200,000
                          Fund


            FM 1938 at West  Funding is requested for right of way, new traffic signal, right turn lane, and other paving improvements to improve the alignment
            Continental   of this intersection based on recommendations of a  engineering study of this intersection.  Drainage improvements will also be
            Boulevard     included with this project, specifically the improvement of Critical Drainage Structure #18.  These improvements will help alleviate
            Intersection   current traffic backups during peak hours on west-bound West Continental Boulevard at FM 1938.  In addition, the project will
            Improvements  also include landscape and irrigation improvements.
                          General
            2022-07c                    $900,000  $400,000  $2,000,000    $0        $0        $0        $0   $3,300,000
                          Fund
                          Storm
            2022-07c      Water Utility      $0        $0   $800,000      $0        $0        $0        $0    $800,000
                          System

                          Total         $900,000  $400,000  $2,800,000    $0        $0        $0        $0   $4,100,000





            Corridor Safety  The purpose of this project is to evaluate and improve upon the existing mobility system within the City to provide enhanced
            Improvements  safety for motorists and pedestrians.



                          Red Light
            2022-08       Camera             $0   $100,000       $0       $0        $0        $0        $0    $100,000
                          Fund




            North Carroll   Funding is planned for traffic improvements including new medians, new turn lanes and lane realignments, new pavement
            Avenue -      markings and improved intersections. This project will improve traffic flow in the North Carroll Avenue corridor between Southlake
            Corridor      Boulevard and State Highway 114 and enhance pedestrian safety.


                          General
            2022-09       Fund               $0        $0   $720,000      $0        $0        $0        $0    $720,000




            State Street &   Funding is planned for traffic improvements including a curbed island and new pavement markings at the intersection of State
            Frontage Road -  Street and State Highway 114. The improvements are based on the recommendation of a traffic study. This project will improve
            Intersection  access at the intersection and enhance pedestrian safety.


                          General
            2022-10       Fund               $0        $0   $160,000      $0        $0        $0        $0    $160,000






                                                                           BUDGET BOOK   |  FY 2022 City of Southlake  387
                                                                                         WWW.CITYOFSOUTHLAKE.COM
   383   384   385   386   387   388   389   390   391   392   393