Street & Sidewalk Capital Projects
Department Project Title Project Number
Public Works Transportation Management Project Equipment ST2102
Project Description
This project will build on the Traffic Management Project approved in the 2019-20 CIP budget by upgrading ten intersections to be
compatible with our new central synchronization software:
1) Rufe Snow: (Meadow Lakes, Loop 820, Tapp, Dick Lewis, Iron Horse, Starnes), 2)Mid-Cities: Iron Horse, Holiday 3) Davis
Blvd.: College Circle, Emerald Hills
The new equipment includes controllers, vehicle detectors and communications systems. The plan is to systematically upgrade
existing traffic signals each year until the entire transportation system is connected and complete.
Project Justification
One of the goals of the Traffic Division is to have the safest and most effective and efficient transportation system. With the
implementation of the new central synchronization software the Traffic Divisions goal is to expand the boundaries from the initial
project to better serve the residents of North Richland Hills. This system will operate using engineer-designed timing plans that are
the basis for the traffic signal coordination. The software and equipment working in concurrence has the ability to communicate with
the Service Center and Traffic Technicians alerting them by email or text message of a malfunctioning traffic signal, which will
reduce signal malfunction down time and delays to motorists. Currently the only way Public Works is notified of a malfunction is by a
resident making a report or City staff member observes it during their shift. The program also has the capabilities to collect traffic
data, which will be used to establish timing plans along these cooridors based on actual demand to address traffic flow and
congestion concerns.
Note: Project funding source is the Street Reserves.
Project Schedule Beginning Date Ending Date History Fiscal Year Amount
Professional Services Adopted Budget 2020-21 $195,550
Engineering/Design Total $195,550
Land/ROW Acquisition
Construction 10/2020 09/2021
Other
Total Schedule 10/2020 09/2021
Sources of Funds Appr. To Date 2021‐22 Budget 2022‐23 Estimate 2023‐Completion Total Funding
General Obligation Bonds
Certificates of Obligation
Federal/State Grants
Reserves 195,550 0 0 0 $195,550
Sales Tax
Other
Total Funding $195,550 $0 $0 $0 $195,550
Project Costs To Date 2021‐22 Budget 2022‐23 Estimate 2023‐Completion Total Cost
Professional Services
Engineering/Design
Land/ROW Acquisition
Construction 195,550 0 0 0 $195,550
Other
Total Costs $195,550 $0 $0 $0 $195,550
Operating Impact
No operating impact is anticipated.
Fiscal Year 2020‐21 2021‐22 2022‐23 2023‐24 2024‐25 Total Impact
Amount $0 $0 $0 $0 $0 $0