Page 287 - Project Detail Sheet_AdoptedBook
P. 287
ADOPTED | BUDGET
Economic Development Capital Projects
Department Project Title Project Number
Economic Development Sign Removal Assistance Program PW0402
Project Description
This project assists North Richland Hills businesses who voluntarily choose to remove their non-conforming signs. This project is a
cooperative effort between the Planning and Development Department and the Economic Development Department.
Project Justification
Supports the 2001 City Image Study that details issues concerning visual clutter along the City's thoroughfares. In response, the
City Council adopted a program that assists the voluntary removal of non-conforming signs in the 2003-2004 Capital Improvement
Budget. Business owners are not required to remove their signs; however, they may opt for city assistance should they choose to do
so. In concert with the Business Improvement and Growth (BIG) program, business owners can partner with the City on each site-
specific project by contacting or working with staff for inclusion in the Sign Removal Assistance Program. New business owners
cannot modify or change their non-conforming signs except under very limited conditions.
For eligible BIG program participants, the maximum sign removal assistance provided is $2,000 per program participant.
Note: The source of funds originate from the General Fund 'pay-as-you-go' reserve.
Project Schedule Beginning Date Ending Date History Fiscal Year Amount
Professional Services Adopted Budget 2003-04 $20,000
Engineering/Design Revision 2007-08 $20,000
Land/ROW Acquisition Revision 2009-10 $10,000
Construction Total $50,000
Other 10/2003 09/2022
Total Schedule 10/2003 09/2022
Sources of Funds Appr. To Date 2021‐22 Budget 2022‐23 Estimate 2023‐Completion Total Funding
General Obligation Bonds
Certificates of Obligation
Federal/State Grants
Reserves 50,000 0 0 0 $50,000
Sales Tax
Other
Total Funding $50,000 $0 $0 $0 $50,000
Project Costs To Date 2021‐22 Budget 2022‐23 Estimate 2023‐Completion Total Cost
Professional Services
Engineering/Design
Land/ROW Acquisition
Construction
Other 50,000 0 0 0 $50,000
Total Costs $50,000 $0 $0 $0 $50,000
Operating Impact
No additional operating impact.
Fiscal Year 2020‐21 2021‐22 2022‐23 2023‐24 2024‐25 Total Impact
Amount $0 $0 $0 $0 $0 $0