Average Home Levy
                         $1,500
                                               $1,410     $1,402     $1,421
                         $1,400    $1,362                                      $1,390     $1,374

                         $1,300

                         $1,200


                         $1,100

                         $1,000
                                   2016‐17    2017‐18    2018‐19    2019‐20    2020‐21    2021‐22


               Strategy 3.4: Protect Taxpayers’ Interests

               City Council continues to recognize the need to be proactive when it comes to planning for repairs and
               replacements of capital investments and critical equipment. Aimed at cash funding future projects rather
               than issuing debt, in FY 2019‐20 the council approved a Fire/EMS replacement program that will set aside
               money annually to pay for expected equipment replacements. The Fire/EMS replacement program is the
               latest addition to the city’s replacement allocations, which include accounts for fire apparatus, vehicles,
               heavy equipment, technology and city facilities. The FY 2021‐22 General Fund budget will continue these
               annual transfers, ensuring that equipment will be promptly repaired or replaced when it has reached the
               end of its useful life.

               The FY 2021‐22 Adopted Budget also continues council’s commitment to cash funding capital projects
               whenever possible. There are nearly $10.2 million in street improvements, $6.2 million in water system
               improvements, $3.8 million in wastewater system improvements, $2 million in park improvements, and
               $425,000 in drainage system improvements included in FY 2021‐22. The total capital project investment,
               all of which will be cash funded, is approximately $22.6 million.

               Looking ahead, the city’s Capital Improvements Plan forecasts $108.5 million in city capital expenditures
               over the next five years and anticipates issuing $50.4 million in debt, or 46.4%. The proposed debt includes
               the  issuance  of  up  to  $25  million  for  street  system  improvements,  $14.3  million  for  water  system
               improvements, and $11.1 million for wastewater system improvements.
               Debt issuances on the horizon can be found in the city’s five‐year Capital Improvements Plan. Below is a
               list of the projects related to the proposed debt issuances:

                     Old Town Keller East/Bates Street projects
                     Whitley Road Reconstruction project
                     2023 SWIFT project
                     Pump Station Rehabilitation
                     Johnson Road 12” Water Lines






                                                             22
   19   20   21   22   23   24   25   26   27   28   29