Impact of Capital / Street Maintenance Projects to Operating Budget

               Some projects may have a fiscal impact to the City’s operating funds as routine maintenance and
               operational expenditures are necessary to utilize the completed project.  When an operating
               impact has been identified, it is included on the project description sheet, and costs are projected
               for the next three years.  Upon approval of the project for annual expenditure, the fiscal impact is
               integrated into the operating budget.

               The estimated operating budget impact of Facilities Maintenance projects is calculated on a cost
               per square-foot basis.  The comprehensive preventative maintenance program implemented for
               general facilities incorporates tasks such as  routine repairs, preventive  maintenance and
               replacement costs.  The amount is adjusted annually for inflation.


               Square Footage Maintained                554,551
               Cost per Square Foot                       $0.75
               Estimated Operating Impact              $415,913


               Capital / Street Maintenance Long-Range Planning Process

               The long-range planning process is used as a tool to identify major capital maintenance needs in
               advance of requirement.  By identifying major needs in advance, projects can then be ranked and
               prioritized.  The long-range plan  can  also be used to reduce the severity  of major spikes in
               maintenance costs.

               The planning process for Facilities and Parks maintenance is a five-year plan by facility and
               maintenance activity or project.  The Facilities Services division of the Public Works department
               prioritizes other departmental requests for projects along with known maintenance requirements.

               The Parks  and Recreation department schedules identified  ground improvements maintenance
               projects according to priorities and funding level. The long-range planning effort provides for a
               stable annual level of expenditures to ensure the continued maintenance of general purpose and
               recreational facilities and grounds.

               The Planning process for Street maintenance is  a five-year plan to maintain and improve the
               City’s roadways, sidewalks, signals, signs and pavement markings.  The Public  Works
               department is responsible for the surface repair and preventive maintenance of streets throughout
               the City. This is accomplished by reducing pavement deterioration with proper maintenance
               techniques and systematic inspection.   The program of work resurfaces 130,000 square yards, or
               8.2 miles of streets annually, repairs 800 linear feet of deteriorated curb and gutter, and crack
               seals 200 blocks each year.