Page 268 - Microsoft Word - FY 2022 Adopted Budget Document
P. 268
Capital Improvement Program to Table of Contents
Return to Table of Contents
Return
Certificates of Obligation
Five Year History
Fiscal Final Cost or Completion
Year Department Project Amount Cost to Date Status Start Date Date
2017 Fire Fire Apparatus $1,725,000 $1,723,855 Completed Mar-18 May-18
2017 IT IT Infrastructure $1,800,000 $1,763,248 Completed Aug-18 N/A
2017 Sub-Total $3,525,000 $3,487,103
2018 Public Works & Trans. Facility Maintenance $3,200,000 $2,115,696 Completed Feb-18 N/A
2018 IT IT Infrastructure $1,975,000 $544,809 Completed Aug-18 N/A
2018 Sub-Total $5,175,000 $2,660,504
2019 Fire Fire Heavy Fleet Replacement $2,692,336 $2,692,336 Completed Apr-19 Oct-19
2019 Parks Tiera Verde HVAC $750,000 $612,012 Completed Mar-19 Sep-20
2019 Parks Playground Replacement $1,140,000 $863,348 Completed Sep-19 Jan-21
2019 Parks River Legacy Parking Lot Renovations $350,000 $0 In-progress N/A N/A
2019 Public Works & Trans. Facility Maintenance $1,000,000 $223,441 In-progress N/A N/A
2019 Sub-Total $13,042,336 $8,013,345
2020 Fire Aircraft Rescue & Firefighting (ARFF Unit) $750,000 $0 In-progress N/A N/A
2020 Fire Fire Heavy Fleet Replacement $655,000 $655,000 Completed Apr-20 Apr-20
2020 Fire Dispatch Services CAD Data Storage $800,000 $581,388 In-progress Apr-20 Apr-20
2020 N/A Storm Water Infrastructure $3,200,000 $0 In-progress N/A N/A
2020 N/A Radio Lease $4,915,000 $4,915,000 Completed Oct-20 Jun-21
2020 Sub-Total $15,235,000 $6,151,388
2021 N/A No CO's Sold $0 $0 N/A N/A N/A
2021 Sub-Total $0 $0
Grand Total $36,977,336 $20,312,340