Capital Improvement Program                                                      to  Table  of  Contents
                                                                                                   Return to Table of Contents
                                                                                                   Return


                                                   Certificates of Obligation
                                                       Five Year History
             Fiscal                                                         Final Cost or               Completion
              Year     Department              Project            Amount    Cost to Date  Status  Start Date  Date
              2017  Fire                             Fire  Apparatus  $1,725,000  $1,723,855 Completed  Mar-18  May-18
              2017  IT                               IT  Infrastructure  $1,800,000  $1,763,248 Completed  Aug-18  N/A
                                                     2017 Sub-Total  $3,525,000  $3,487,103


              2018  Public Works & Trans.         Facility Maintenance  $3,200,000  $2,115,696 Completed  Feb-18  N/A
              2018  IT                               IT  Infrastructure  $1,975,000  $544,809 Completed  Aug-18  N/A
                                                     2018 Sub-Total  $5,175,000  $2,660,504


              2019  Fire                  Fire Heavy Fleet Replacement  $2,692,336  $2,692,336 Completed  Apr-19  Oct-19
              2019  Parks                          Tiera Verde HVAC  $750,000  $612,012 Completed  Mar-19  Sep-20
              2019  Parks                     Playground Replacement  $1,140,000  $863,348 Completed  Sep-19  Jan-21
              2019  Parks            River Legacy Parking Lot Renovations  $350,000  $0 In-progress  N/A   N/A
              2019  Public Works & Trans.         Facility Maintenance  $1,000,000  $223,441 In-progress  N/A  N/A
                                                     2019 Sub-Total  $13,042,336  $8,013,345

              2020  Fire           Aircraft Rescue & Firefighting (ARFF Unit)  $750,000  $0 In-progress  N/A  N/A
              2020  Fire                  Fire Heavy Fleet Replacement  $655,000  $655,000 Completed  Apr-20  Apr-20
              2020  Fire              Dispatch Services CAD Data Storage  $800,000  $581,388 In-progress  Apr-20  Apr-20
              2020  N/A                       Storm Water Infrastructure  $3,200,000  $0 In-progress  N/A  N/A
              2020  N/A                                Radio Lease  $4,915,000  $4,915,000 Completed  Oct-20  Jun-21
                                                     2020 Sub-Total  $15,235,000  $6,151,388

              2021  N/A                               No CO's Sold      $0         $0    N/A     N/A       N/A
                                                     2021 Sub-Total     $0         $0




                                                       Grand Total  $36,977,336  $20,312,340