Page 301 - N. Richland Hills Capital Budget
P. 301

Parks & Recreation Capital Projects
                                                    Park System Signage
                                                           PK1606


           PROJECT DESCRIPTION & JUSTIFICATION
            This project provides for design and construction of new, updated signage that will provide a gateway to each park, consistent
            with the vision, "City as Park" as supported by the Park, Recreation and Open Space Master Plan.













           PROJECT STATUS                         ORIGINAL      2019/20                   ORIGINAL      2019/20
                                                 START DATE    REVISION                   END DATE     REVISION

           Professional Services
           Engineering
           Land/ROW Acquisition
           Construction                           10/2015                                 04/2020       08/2020
           Other

           REVISION EXPLANATION
            This project will have significant savings when all work is completed. The funding is being provided to PK1806 to support
            additional requested professional services.



           FINANCIAL DATA
                                                  ADOPTED                    REVISED                    TOTAL
                                                BUDGET THRU    PROJECT     BUDGET THRU   REMAINING     PROJECT
                                                   2019/20     REVISION      2019/20      BALANCE        COST
           FUNDING SOURCES
            Sales Tax                               $479,486      ($5,000)          $0                   $474,486


                                                                                     0                         $0
                                                                                     0
                                                                                     0                         $0
           Total                                    $479,486      ($5,000)          $0           $0      $474,486
           PROJECT EXPENDITURES
             Professional Services
             Engineering/Design                                                      0                         $0
             Land/ROW Acquistion                                                     0                         $0
             Construction                            479,486       (5,000)           0                   $474,486
             Other                                                                   0
           Total                                    $479,486      ($5,000)                       $0      $474,486

           IMPACT ON OPERATING BUDGET




           ANNUAL OPERATING IMPACT     2019/20     2020/21       2021/22     2022/23      2023/24       TOTAL
           Projected                                                                                           $0