Utility Capital Projects



           Project Name                                      Project Description
         Matson Drive Sanitary Sewer -   This is the 46th Year Community Development Block Grant (CDBG) Project.  The project will consist of reconstructing
         New Project             approximately 1,300 linear feet of sanitary sewer main.








         Miscellaneous Water/Sewer   This is an annual program that is completed by the Public Works Construction Division. The program will provide for
         Main Replacement (2020) -   water and sewer main replacements including any developmental projects. The project replaces aging infrastructure and
         Continuing Project      maintains high standards for water quality. This will include replacements on the following streets: Oldham Place
                                 (Buckingham Trail - Yarmouth Avenue), Shadydale Drive (Meadowview Ter. - Crosstimbers Lane), Southampton Road
                                 (Chapman Road - Wakefield Road) and Susan Court (Scott Drive - 7533 Susan Court).






         Miscellaneous Water/Sewer   This is an annual program that is performed by the Public Works Construction Division.  The program will provide for
         Main Replacement (2021) - New   the construction of water and wastewater main replacements to include possible development projects.  The project
         Project                 replaces the aging and undersized water and wastewater infrastructure. This year's scope is expected to include
                                 water/sewer main replacements on the following streets: Edinburg Drive (Brookshire to Wakefield), Circle Drive (Susan
                                 Lee to Cul-de-sac), Bogart (College Circle to Price), Spring Lea Way (Starnes to Lincoln) and Southampton Drive
                                 (Wakefield to Chapman).





         Motor Operated Transfer   This project consists of motor operated valves to be placed on existing water lines at three locations along Holiday Lane,
         Valves - Continuing Project  Thaxton Parkway, and Boulevard 26.








         Sanitary Sewer System   This project will consist of replacing approximately 1,200 linear feet of sanitary sewer main lines in North Richland Hills.
         Rehabilitation (Various   In addition five manholes will be replaced. Streets included in this project will be Nancy Lane (4900 to 5000 block);
         Locations) - Continuing Project  8020 Laura Street to 8017 Lazy Street; and 7000 to 7028 Smithfield Road.








         Sanitary Sewer System Trunk   This project will reconstruct approximately 550 feet of 18 inch sanitary sewer line. The line is located near the drainage
         Line Rehabilitation - Continuing   ditch and channel for Mackey Creek. The project will start at the existing line located near Jackie Lee and end near
         Project                 Harmonson Road.