               Water                                  2021       2022        2023       2024       2025        Total

               Water Renewals
               Pleasant Run Road Waterline (John
               McCain North to Bear Creek) -         $850,000     —           —          —           —         $850,000
               Construction
               Water Project 10: Apple Valley/Rustic
               Oaks/Bills Lane Water Lines and Road   $630,000    —           —          —           —         $630,000
               Rehabilitation on Black Drive and Rustic
               Trail
               Water Project 12: Woodbriar Estates -   $100,000   —           —          —           —         $100,000
               Design
               Water Project 18: Pecan Park Estates-  $120,000    —           —          —           —         $120,000
               Design

               Water Project 6: Quail Crest - Design   $150,000   —           —          —           —         $150,000

               Water Project 12: Woodbriar Estates -   —       $1,000,000     —          —           —       $1,000,000
               Construction
               Water Project 16: Timberline Drive -    —        $200,000      —          —           —         $200,000
               Design
               Water Project 18: Pecan Park Estates-   —        $800,000      —          —           —         $800,000
               Construction
               Water Project 5: Brighton Oaks - Design   —      $250,000      —          —           —         $250,000

               Water Project 6: Quail Crest -
               Construction                            —        $700,000      —          —           —         $700,000
               Water Project 16: Timberline Drive -    —          —       $2,500,000     —           —       $2,500,000
               Construction
               Water Project 5: Brighton Oaks          —          —       $2,550,000     —           —       $2,550,000
               Water/Street Rehabilitation
               Water Project 14: Mixed Use             —          —         $200,000     —           —         $200,000
               Connections-Design
               Water Project 14: Mixed Use             —          —           —       $1,700,000     —       $1,700,000
               Connections-Construction

               Water Project 17: Monticello - Design   —          —           —        $200,000      —         $200,000

               Water Project 13: Glade at Old Oak and
               SH121 - Design                          —          —           —          —        $200,000     $200,000
               Water Project 17: Monticello -          —          —           —          —       $3,000,000   $3,000,000
               Construction
               Water Total                         $1,850,000  $2,950,000  $5,250,000  $1,900,000  $3,200,000  $15,150,000

              Exhibits

                   A.  Fiscal Year 2021 Individual Project Pages
                   B.  Fund Balance
                   C.  5 Year Capital Improvement Plan FY2021-2025 - Project List
                                                             237
   234   235   236   237   238   239   240   241   242   243   244